Mumbai/Project record

MahaRERA · the public record

DASHMESH PALACE

Block No A-261 Room No 522 · JOHNY NANDLAL SACHDEV

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700030189

Delivery and registration

When is the project declared for completion?

DASHMESH PALACE is registered with MahaRERA as P51700030189 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700030189
Registered on05 Aug 2021
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DASHMESH PALACE record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Johny Nandlal Sachdev is the promoter of record on 7 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DASHMESH PALACE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
DASHMESH PALACE1G+630 Sep 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Block No A-261 Room No 522, KURLA CAMP, Ulhasnagar, Thane, 421004. Per the filed land record, the plot is bounded to the north by Road, to the south by Room on Govt Land, to the east by Block No A-261 Room No522 and to the west by Room on Govt Land. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ulhasnagar

Ganga Residency
possession by Sep 2026 · MR Ravi Yallappa Vhatkar
Jhalak Arena
possession by Dec 2026 · Jhalak Constructions
Roshan Galaxy
possession by Dec 2026 · Royal Group
SEA Green Aurus
possession by Feb 2027 · Sea Green Homes
Elite Crystal
possession by Jun 2027 · Elite Ulhas
Fortune Galaxy
possession by Jul 2027 · Sai Construction

Other RERA-registered projects in Thane

Dashmesh Pearl
possession by Dec 2026 · Empire Realty
Datar Height D AND E Wing
possession by Dec 2028 · Not Available
Datar Sadan CHS LTD
possession by Dec 2029 · SAI Prasad Builders AND Developers
Datta Ashoka
possession by Dec 2029 · Southfield Realty LLP
Datta Kutir
possession by May 2027 · Sparsh Buildcon
Datta Samarth
declared completion Jun 2026 · Pandurang Arjun Chawan

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026