MahaRERA Property Intelligence · Raigarh

DDSR Satvic

P52000050488 · Kalamboli · promoter Ddsr Builders And

Certificate SignedDue 31 Mar 2026

Delivery & Registration

MahaRERA registrationP52000050488
Registered on17 Apr 2023
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ddsr Builders And is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
DDSR Satvic1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
15 Mar 202531 Mar 2026We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues

Location, Land & Connectivity

Located at Kalamboli, Sector No- 11, Panvel, Raigarh, 410218. Per the filed land record, the plot is bounded to the north by Diversion Channel, to the south by Plot No-6 and 8M Wide Road, to the east by Plot No-5 Garden and to the west by Plot No- 6B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Bandra Kurla Complex (BKC)25 km
Chhatrapati Shivaji Int'l Airport26 km
Andheri MIDC / SEEPZ27 km
Lower Parel / Worli business district29 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ddsr Builders And Developers LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Ddsr Builders And Developers LLP

Ddsr Builders And Developers LLP
FlaggedRaigarh

Other RERA-registered projects in Kalamboli

Century Heights
possession by Sep 2026 · Prabhu Virji Patel
Manisha Paradise
possession by Dec 2026 · Pruthvi Builders & Developers
Bhaveshwar Aqua - 2
possession by Dec 2026 · Bhaveshwar Infratech
Century Dreams
possession by Dec 2026 · Mukesh Premji Patel
Ddsr Heights
possession by Dec 2026 · Ddsr Builders And Developers LLP
Millennium Urbania
possession by Dec 2026 · Millennium Group

Other RERA-registered projects in Raigarh

Deccan Pride
possession by Mar 2030 · Praveen Premkumar Nair
Deccan Residency
declared completion Mar 2019 · Praveen Premkumar Nair
Deccan Residency
declared completion Dec 2024 · Praveen Premkumar Nair
Deccan Square
declared completion Oct 2024 · Afzal Umer Furniturewala
Decent Apartment
declared completion Apr 2021 · Decent Builders & Developers
Decent Apartments
declared completion Dec 2025 · Shibam Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026