Plotted Development Intelligence · Palghar

DES

P99000010537 · promoter Acropolis Infrastructure Development

Certificate SignedDue 31 Aug 2019

Delivery & Registration

MahaRERA registrationP99000010537
Registered on31 Aug 2017
Promoter-declared completion31 Aug 2019
Current statusCertificate Signed
Against todayabout 83 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Acropolis Infrastructure Development is the promoter of record on 4 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 239 plots filed with MahaRERA, 123 are sold/booked and 116 remain available (~51% sold) — selling steadily. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000096702/10/2017Mahendra Naranji Thakkar/Yogendra Naranji Thakkar vs Sachin Kalraorder passed
CC00600000005617112/09/2018BHARATI KOTHARI vs SACHIN KALRAorder passed
CC00600000005704304/12/2018Pranav Shah vs Sachin Kalra, Acropolis Infrastructure Developmentorder passed
CC00600000005814328/02/2019Bhupinder pal Singh vs Acropolis Infrastructure Developmentorder passed
CC00600000019291606/03/2020Manoj Shah vs Sachin Karlaorder passed
CC1250150706/05/2025walter anthony dsouza vs Acropolis infrastructure developmentorder passed

Location, Land & Connectivity

Located at Khandeghar Village, Mumbai City, Mumbai City, 401605. Per the filed land record, the plot is bounded to the north by 21, to the south by kunjharge gaon, to the east by 23 26 27 31 32 and to the west by 34 22. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~78 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ78 km
Powai / Hiranandani business park78 km
Chhatrapati Shivaji Int'l Airport82 km
Bandra Kurla Complex (BKC)85 km
Lower Parel / Worli business district93 km
Nariman Point / Fort101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vikramgad

Shree Hari Complex
possession by Dec 2028 · V. G. Construction
Narayani Residency`
possession by May 2030 · Himanshu Sham Tendulkar
Baandhan Heritage II
declared completion Dec 2025 · Mahi Links
Banndhan Heritage I
declared completion Dec 2025 · Mahi Links
Arihant Residency
Not filing quarterly progress reports · declared completion Jun 2025 · Sheetal Construction
Gurukrupa Residency
declared completion May 2025 · Shree Swami Samarth Developers

Other RERA-registered projects in Palghar

DEV Darshan
possession by Sep 2026 · Ashray Infra Builders & Developers
DEV Laksh Pride
possession by Jan 2027 · United Developers
Deva Rudant Heights
possession by Jan 2028 · Deva Rudant Enterprises
Devakinagar
declared completion Apr 2022 · Empire Developers
Devashish Park
declared completion Dec 2024 · Ramjeet Kewat
Devi Krupa
possession by Dec 2026 · Vira Links LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026