Mumbai/Project record

MahaRERA · the public record

DES

Mumbai City · Acropolis infrastructure development

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

116units filed as unsoldInventory · 16 September 2026
31 Aug 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000010537

Delivery and registration

When is the project declared for completion?

DES is registered with MahaRERA as P99000010537 and the promoter has declared completion for 31 Aug 2019.

31 Aug 2019

declared completion

85months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000010537
Registered on31 Aug 2017
Promoter-declared completion31 Aug 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DES record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Acropolis Infrastructure Development is the promoter of record on 5 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In DES, 123 of 239 plots filed with MahaRERA are recorded as sold or booked, about 51%, and 116 remain available.

51%sold

123 of 239 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What the filings record, plot by plot

Read from MahaRERA on 16 September 2026

MahaRERA publishes, plot by plot, what this promoter filed: which plots are sold and which are not, the filed area of each, and for the sold ones the registered agreement value — the consideration filed for that specific plot. On this project 123 plots carry one, and 116 of the 239 are recorded unsold.

Here is one of those unsold plots, priced against what buyers of comparable plots on the same filing actually filed:

PlotAreaFiled for comparable plots on the same filingBased on
1151,203,404 sqftRs 2.71 lakh typical, over Rs 0.81 lakh to Rs 12.21 lakh123 filed at this size

A filed consideration is what was registered for one plot. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the plot is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In DES, 89 of the 116 unsold plots have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 115 plots — ₹2,999 →

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for DES, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000096702/10/2017Mahendra Naranji Thakkar/Yogendra Naranji Thakkar vs Sachin Kalraorder passed
CC00600000005617112/09/2018BHARATI KOTHARI vs SACHIN KALRAorder passed
CC00600000005704304/12/2018Pranav Shah vs Sachin Kalra, Acropolis Infrastructure Developmentorder passed
CC00600000005814328/02/2019Bhupinder pal Singh vs Acropolis Infrastructure Developmentorder passed
CC00600000019291606/03/2020Manoj Shah vs Sachin Karlaorder passed
CC1250150706/05/2025walter anthony dsouza vs Acropolis infrastructure developmentorder passed

Location, Land & Connectivity

Located at Khandeghar Village, Mumbai City, Mumbai City, 401605. Per the filed land record, the plot is bounded to the north by 21, to the south by kunjharge gaon, to the east by 23 26 27 31 32 and to the west by 34 22. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~78 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ78 km
Powai / Hiranandani business park78 km
Chhatrapati Shivaji Int'l Airport82 km
Bandra Kurla Complex (BKC)85 km
Lower Parel / Worli business district93 km
Nariman Point / Fort101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vikramgad

Shree Hari Complex
possession by Dec 2028 · V. G. Construction
Narayani Residency`
possession by May 2030 · Himanshu Sham Tendulkar
Baandhan Heritage II
declared completion Dec 2025 · Mahi Links
Banndhan Heritage I
declared completion Dec 2025 · Mahi Links
Arihant Residency
Not filing quarterly progress reports · declared completion Jun 2025 · Sheetal Construction
La Manor
declared completion Sep 2024 · Rajaram Balwant Patil

Other RERA-registered projects in Palghar

DEV Laksh Pride
possession by Jan 2027 · United Developers
Devashish Park
declared completion Dec 2024 · Ramjeet Kewat
Devashree Apartment
declared completion Dec 2022 · Abhishek Mahesh Chowdhary
Devshrishti Complex Bldg NO 1, Wing-F
declared completion Dec 2022 · Tirupati Developers
DEW Berry Building NO 5 Wing F TO J
declared completion Jun 2022 · Shree SAI Shakti Enterpraises
Dhananjay AND Hayaat Industrial Estate
possession by Dec 2028 · M M Infra Project

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026