Mumbai/Project record

MahaRERA · the public record

DEV RESIDENCY

Raigarh · Devkrupa Enterprises

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

10 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000014331

Delivery and registration

When is the project declared for completion?

DEV RESIDENCY is registered with MahaRERA as P52000014331 and the promoter has declared completion for 10 Dec 2022.

10 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000014331
Registered on23 Nov 2017
Promoter-declared completion10 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DEV RESIDENCY record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Devkrupa Enterprises is the promoter of record on 6 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DEV RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
DEV RESIDENCY1G+810 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Panvel55/122016Ongoing
Panvel503/122016Ongoing
Panvel619/112016Ongoing

Location, Land & Connectivity

Located at Panvel, Raigarh, 410210. Per the filed land record, the plot is bounded to the north by PLOT NO 2A-2, to the south by PLOT NO 11, to the east by PLOT NO 5 AND 6 and to the west by 11 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Bandra Kurla Complex (BKC)21 km
Chhatrapati Shivaji Int'l Airport22 km
Andheri MIDC / SEEPZ22 km
Lower Parel / Worli business district26 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Devkrupa Enterprises is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Kharghar

Tharwani Palladian
possession by Sep 2026 · Tharwani Realtors
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary
Krishna Aura
possession by Oct 2026 · Qualitas Lifespaces LLP
Ashwini Apartment
possession by Dec 2026 · Kuldeepsingh Amarsingh Bhalothia
Bhagwati Luxuria
possession by Dec 2026 · Bhagwati Signature LLP
Elysian
possession by Dec 2026 · Devam Ventures

Major developers building in Kharghar

Other RERA-registered projects in Raigarh

DEV Residency
declared completion Sep 2023 · Devinfra Builders AND Developers LLP
DEV Residency
declared completion Dec 2025 · Dev Varsha Construction
Devam Residency
declared completion Dec 2022 · Vinodbhai Muljibhai Ravriy
Devansh
declared completion Jun 2026 · Platinum Enterprise
Devashree Aangan
possession by Dec 2026 · Shashikant Maruti Disale
Devike Construction
declared completion Dec 2022 · Suresh Ganpat More

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026