MahaRERA Property Intelligence · Palghar

DOHA LIFESPACE

P99000020442 · SAPHALE WEST · promoter Doha Lifespace Developers

Certificate SignedDue 30 Dec 2024

Delivery & Registration

MahaRERA registrationP99000020442
Registered on10 Apr 2019
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
DOHA LIFE SPACE WING A1G+431 Dec 2023
DOHA LEFESPACE WING B1G+431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SAPHALE WEST, MAKANE VIRATHAN ROAD, Palghar, Palghar, 401102. Per the filed land record, the plot is bounded to the north by 232, to the south by ROAD, to the east by 222 and to the west by 225. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Makane

Galaxy Complex
possession by Jul 2026 · Ksquare Realty Private Limited
Balaji Heights
possession by Dec 2026 · Tirupati Enterprises
Excellence Residency 2
possession by Dec 2026 · SAI Excellence Realtors
Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra

Major developers building in Makane

Other RERA-registered projects in Palghar

Donde Heights
declared completion Mar 2023 · Guruprabhu Realtors
Dosti Heights
possession by Mar 2027 · SAI Crystal Builders
Draupadi Darshan
possession by Dec 2028 · Darshan Builders AND Developers
Dream Aura
possession by Dec 2026 · Clement Regency Developers
Dream City
declared completion Jul 2025 · Vishal Dilip Sankhe HUF
Dream Nest
declared completion Jun 2026 · M/s. Clement Regency Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026