MahaRERA Property Intelligence · Thane

DZ CITY - BUILDING NO 2

P51700030874 · MUMBRA · promoter Al Ameen Builders

Certificate SignedDue 30 Jun 2026

Delivery & Registration

MahaRERA registrationP51700030874
Registered on20 Sep 2021
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Al Ameen Builders is the promoter of record on 4 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~29.7% of the estimated project cost incurred as of the last certificate (₹13.75 Cr spent against a ₹46.34 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~29.7% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 109 homes filed with MahaRERA, 47 are sold/booked (23 with registered agreements + 24 booked) and 62 remain available (~43% sold) — selling steadily. Buyers have committed ₹16.26 Cr in agreement value so far. Of that, ₹8.04 Cr (~49%) is already collected, ₹8.22 Cr receivable — a read on how far along these sales really are. Note: the project registers 182 homes in total, but this sold/unsold inventory filing covers only 109 of them — the other 73 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 47 registered agreements, the effective carpet rate is ₹6,208/sqft (typical range ₹5,321–₹6,219) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

⚠ The inventory filing also declares: 11 reserved and 62 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21 and 182 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
DZ CITY - BUILDING NO 21G+2118230 Jun 2026

Unit mix on the filing: 155 residential and 27 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MUMBRA, OLD MUMBAI PUNE ROAD, Thane, Thane, 400612. Per the filed land record, the plot is bounded to the north by MITTAL GROUND, to the south by 30MT MAULANA AZAD ROAD, to the east by 20MT DP ROAD and to the west by 45MT MUMBAI PUNE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

AL Ameen Builders AND Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Mumbra

Celosia Avenue
possession by Sep 2026 · Pratima Construction
Quality Annex
possession by Sep 2026 · Quality Annex
YES Central Galleria
possession by Oct 2026 · Noble Enterprises
YES Central Galleria 1
possession by Oct 2026 · YES Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

Major developers building in Mumbra

Other RERA-registered projects in Thane

DZ City - Building NO 3
declared completion Jun 2026 · AL Bari's Construction
E.v.paradise
possession by Mar 2031 · EV Homes Constructions Pvt. Ltd.
Eagleridge Wing A
declared completion Jul 2025 · Roma Builders Private Limited
Eagleridge Wing B
declared completion Jul 2025 · Roma Builders Private Limited
Eagleton
declared completion Dec 2022 · Roma Builders Private Limited
Earth Park Building NO 1
possession by Dec 2031 · Aastha Housing Corporation

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026