Mumbai/Project record

MahaRERA · the public record

Enrich Eva

Shahapur · DEVDAS TUKARAM CHAUGHULE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700014605

Delivery and registration

When is the project declared for completion?

Enrich Eva is registered with MahaRERA as P51700014605 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700014605
Registered on15 Dec 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Enrich Eva record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Enrich Eva in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Prima1G+4-
Viviana1G+4-
Suprema1G+4-
Regalia1G+4-
Serena1G+4-
Elite1G+4-
Paseo1G+4-
Majestica1G+4-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Enrich Eva, with orders passed in 0 of them.

5complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260009106/01/2026Edwin Juje Fernandes vs DEVDAS TUKARAM CHAUGHULEpending / no order on file
CC1260044324/01/2026Darshana Deepak Sarwankar vs DEVDAS TUKARAM CHAUGHULEpending / no order on file
CC1260046125/01/2026Rahul Prahlad Sharma vs DEVDAS TUKARAM CHAUGHULEpending / no order on file
CC1260050629/01/2026Sangharakshit Ramji Kadam vs Enrich Housingpending / no order on file
CC1260049327/01/2026Princy Swapnil Hule vs DEVDAS TUKARAM CHAUGHULEpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2026I, Devdas Tukaram Chaughule, the promoter of the project Enrich Eva (Registration No. P51700014605) under MahaRERA, hereby submit our request for an extension of time for the compl

Location, Land & Connectivity

Located at Shahapur, Thane, Thane, 421601. Per the filed land record, the plot is bounded to the north by ADJ Gut 21, to the south by ADJ Gut 21, to the east by ADJ Gut 241 and to the west by ADJ Gut 21. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~59 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park59 km
Andheri MIDC / SEEPZ61 km
Chhatrapati Shivaji Int'l Airport64 km
Bandra Kurla Complex (BKC)65 km
Lower Parel / Worli business district73 km
Nariman Point / Fort79 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Enviro Affinity
possession by Dec 2028 · Aristone Developers
EOS IT Park
possession by Dec 2027 · Adyah Ventures
Equinox
possession by Dec 2028 · Shreenath Enterprises
Esquire
possession by Dec 2027 · JP Infra&salasar Buildcon LLP
Estella - Tower C And D
possession by Jun 2032 · Agile Real Estate DEV Private Limited
Estrella Villas
possession by Jan 2027 · Bhavya Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026