ESSAR APEX

Virar West · ARSIWALA CONSTRUCTIONS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

8units filed as unsoldInventory · 16 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000010587

Delivery and registration

When is the project declared for completion?

ESSAR APEX is registered with MahaRERA as P99000010587 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000010587
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ESSAR APEX record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 47 homes carry one, and 8 of the 55 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
11012,119 sqftRs 39.73 lakh typical, over Rs 25.17 lakh to Rs 42.56 lakh11 filed on this stack, floors 1–12

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In ESSAR APEX, 7 of the 8 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 7 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
ESSAR APEX1G+1330 Jun 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ESSAR APEX, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008971112/06/2019Abhishek Kumar Srivastava vs Fakruddin Arsiwalaorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2022In this regards we like to state that our construction work at site is completed 100% and we have also given possession to few flat holders, but due to Covid-19 pandemic and Lockdo
31 Dec 202231 May 2024Date: 25th August, 2023. To, The Maharashtra Real Estate Regulatory Authority (RERA) Mumbai Dear Sir/Madam, Sub: Application for Extension of Project R
31 May 202431 Dec 2025Date: 02th August, 2024 To, The Maharashtra Real Estate Regulatory Authority (RERA) Mumbai Dear Sir/Madam, Sub: Application for Extension of Project Re

Location, Land & Connectivity

Located at Virar West, Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by A-WING, to the south by C-WING, to the east by ROAD and to the west by RECREATIONAL GROUND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~38 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ38 km
Powai / Hiranandani business park41 km
Chhatrapati Shivaji Int'l Airport43 km
Bandra Kurla Complex (BKC)45 km
Lower Parel / Worli business district53 km
Nariman Point / Fort61 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar West

Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers
Sugandhi Square
possession by Dec 2026 · R. N. Realty
Vitthal Haven
possession by Dec 2026 · Sushila Builders & Developers

Other RERA-registered projects in Palghar

Estquire Harmony
possession by Dec 2026 · Estquire Projects Private Limited
Estquire Paradise Phase 2
possession by Dec 2028 · Estquire Projects Private Limited
Estquires Arunoday Presidential Palace
possession by Jun 2029 · Estquire Projects Private Limited
EVA Residency
possession by Dec 2026 · Jayesh Bhagwanbhai Kalsariya
Evara
possession by Dec 2030 · Neminath Poonam Realty LLP
Evergreen Apartment
declared completion Dec 2020 · A J Enterprise

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026