EVERSHINE AMAVI 303 PHASE 1

P99000024780 · Global City Virar West · promoter Evershine Developers

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP99000024780
Registered on05 Mar 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Evershine Developers is the promoter of record on 7 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
BUILDING NO 141G+1530 Dec 2023
BUILDING NO 151G+1530 Dec 2023
BUILDING NO 161G+1530 Dec 2023
BUILDING NO171G+1530 Dec 2023
BUILDING NO 181G+1530 Dec 2023
BUILDING NO 191G+1530 Dec 2023
BUILDING NO 201G+1530 Dec 2023
BUILDING NO 211G+1530 Dec 2023
BUILDING NO 221G+1530 Dec 2023
BUILDING NO 231G+1530 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202329 Dec 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas

Location, Land & Connectivity

Located at Global City Virar West, Chikhadongari Road, Andheri, Mumbai Suburban, 401303. Per the filed land record, the plot is bounded to the north by BUILDING 1 AND 3, to the south by 24 MT WIDE ROAD, to the east by BUILDING 13 AND 24 AND 26 and to the west by NALA. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Evershine Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Evershine Developers

Evershine Developers
FlaggedPalghar
Evershine Developers
FlaggedPalghar
Evershine Developers
FlaggedPalghar

Other RERA-registered projects in Virar West

Padman Residency
Not filing quarterly progress reports · possession by Jul 2026 · Hemant Parshuram Bhoir
Vinay Unique Residency Bldg NO 7
possession by Sep 2026 · Jasamrit Estates Private Limited
Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers

Major developers building in Virar West

Other RERA-registered projects in Palghar

Evershine Amavi 303 Phase 2
declared completion Dec 2024 · Evershine Developers
Evershine Amavi 303 Phase 3
declared completion Dec 2025 · Evershine Developers
Excellence Residency 1
declared completion Dec 2023 · SAI Shraddha Developers
Excellence Residency 2
possession by Dec 2026 · SAI Excellence Realtors
Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
F Clock Tower Phase 1
possession by Dec 2027 · Fawquat Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026