Mumbai/Project record

MahaRERA · the public record

F.W.TOWER

Mumbai City · crystal construction corporation

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

18 Aug 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

18 Aug 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900009073

Delivery and registration

When is the project declared for completion?

F.W.TOWER is registered with MahaRERA as P51900009073 and the promoter has declared completion for 18 Aug 2026.

18 Aug 2026

declared completion

1months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900009073
Registered on19 Aug 2017
Promoter-declared completion18 Aug 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for F.W.TOWER record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Crystal Construction Corporation is the promoter of record on 62 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

62projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for F.W.TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
F W TOWER1G+2522 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ward GNorth, Mumbai City, 400017. Per the filed land record, the plot is bounded to the north by 344, to the south by 388, to the east by DHARAVI ROAD and to the west by 388. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dharavi

Bawa Aashiyaan Phase-II
possession by Dec 2027 · KAY BEE Developers Pvt. Ltd.
CRD Aura
possession by Dec 2027 · CRD Blue Ocean LLP
Bawa Aashiyaan Phase 1
possession by Jun 2028 · KAY BEE Developers Pvt. Ltd.
BKC Edge
possession by Dec 2029 · Labdhi Bliss Private Limited
Prince Tower
declared completion Jun 2025 · Punith Buildtech Private Limited
Samata B SRA CHS LTD
Past its declared completion date · declared completion Jun 2025 · Neeta Builders

Other RERA-registered projects in Mumbai City

Farida Heights
possession by Dec 2026 · Ideal Life Spaces LLP
Fashion Index
declared completion Dec 2023 · PSK Developers Pvt. Ltd.
Fatima Heights
possession by Jan 2027 · M K Enterprises
Fatima Residency
possession by Dec 2027 · M K Enterprises
Fortuna Blue
declared completion Dec 2025 · Alliance Infracorp Developers
Fortune Aura
possession by Dec 2027 · K Realtors

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026