MahaRERA Property Intelligence · Palghar

FIA CONSTRUCTION COMPANY A/C FIA ENIGMA

P99000029742 · PALGHAR · promoter Nimish Laxmichand Pasad

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP99000029742
Registered on29 Jun 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nimish Laxmichand Pasad is the promoter of record on 20 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
FIA ENIGMA1G+831 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PALGHAR, PALGHAR, Palghar, Palghar, 401402. Per the filed land record, the plot is bounded to the north by ROAD, to the south by PLOT NO 67, to the east by PLOT NO 61 and to the west by PLOT NO 63. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nimish Laxmichand Pasad is the promoter on 15 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Nimish Laxmichand Pasad project & its RERA track record →

Other flagged projects by Nimish Laxmichand Pasad

Nimish Laxmichand Pasad
FlaggedPalghar
Nimish Laxmichand Pasad
FlaggedPalghar
Nimish Laxmichand Pasad
FlaggedPalghar
Nimish Laxmichand Pasad
FlaggedPalghar
Nimish Laxmichand Pasad
FlaggedPalghar
Nimish Laxmichand Pasad
FlaggedPalghar

Other RERA-registered projects in Palghar

Sanmukh Sunshine
Not filing quarterly progress reports · possession by Oct 2026 · Sanmukh Realty LLP
Bafna Luxuria
possession by Dec 2026 · Shrushti Developers
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Shakti Industrial Estate
Not filing quarterly progress reports · possession by Dec 2026 · Shakti Krupa Developers
Star Signature City - Star Pearl
possession by Dec 2026 · Star Builders & Developers

Other RERA-registered projects in Palghar

FIA Construction Company FIA Imperia
declared completion Oct 2021 · Nimish Laxmichand Pasad
FIA Construction Company FIA Orion - Grande
declared completion Dec 2025 · Nimish Laxmichand Pasad
FIA Construction Company - FIA Pride
declared completion Dec 2018 · Nimish Laxmichand Pasad
FIA Daffodils
declared completion Dec 2018 · Nimish Laxmichand Pasad
FIA Ekaant
declared completion Feb 2026 · Fia Developers Pvt. Ltd.
FIA Ekdanta
declared completion Dec 2023 · Mystique Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026