Fiora I

Hedutane · LODHA DEVELOPERS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

114units filed as unsoldInventory · 20 September 2026
28 Feb 2030declared completionMahaRERA registration · read 12 Jul 2026
140registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700078112

Delivery and registration

When is the project declared for completion?

Fiora I is registered with MahaRERA as P51700078112 and the promoter has declared completion for 28 Feb 2030.

28 Feb 2030

declared completion

41months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700078112
Registered on25 Nov 2024
Promoter-declared completion28 Feb 2030
Current statusCertificate Signed
Against today41 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Fiora I record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In Fiora I, 0 of 140 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 140 remain available.

0%sold

0 of 140 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 26 homes carry one, and 114 of the 140 are recorded unsold. Since we started watching this ledger, 26 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
0006524 sqftRs 63.69 lakh typical, over Rs 63.14 lakh to Rs 65.05 lakh8 filed on this stack, floors 5–22

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Fiora I, 68 of the 114 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 113 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 140 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Sector O, Cluster 15 Point 04 Wing I1G+23140-

Unit mix on the filing: 140 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered28 Feb 2030Due to management decisions and planning, there was a delay in “Fiora I ” launching the project even after obtaining the RERA number, which resulted in a late start of construction

Location, Land & Connectivity

Located at Hedutane, Hedutane, Mumbai City, Mumbai City, 421203. Per the filed land record, the plot is bounded to the north by 24 by 5pt Hedutane, to the south by 260 by 1 pt Hedutane, to the east by 212 BY 2 part and to the west by 24 by 2 pt Hedutane. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park21 km
Andheri MIDC / SEEPZ24 km
Chhatrapati Shivaji Int'l Airport26 km
Bandra Kurla Complex (BKC)27 km
Lower Parel / Worli business district35 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Hedutane

Ambrin 3
possession by Sep 2026 · Impressions
Liana C
possession by Sep 2026 · Lodha Developers Limited
Casa Belvedere
possession by Oct 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited
Patels Pearl
possession by Oct 2026 · Pramukh Developers
Ashokas Empire
possession by Dec 2026 · Ashokas Empire

Major developers building in Hedutane

Other RERA-registered projects in Thane

Fiora J
possession by Jan 2029 · Lodha Developers Limited
Fiora K
possession by Jan 2028 · Lodha Developers Limited
First Elegance
declared completion Jun 2026 · Gurupreet Singh Baldev Singh Sandhu
Florenza
declared completion Jun 2025 · Nayantara Developers
Flower Valley
declared completion Jun 2022 · Shree Sai Vastu Hills
Flower Valley
declared completion Nov 2025 · Jagani Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.