Mumbai/Project record

MahaRERA · the public record

Gajanan Plaza

Mahavir nagar · Balaji Construction Co.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009622

Delivery and registration

When is the project declared for completion?

Gajanan Plaza is registered with MahaRERA as P51800009622 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009622
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gajanan Plaza record 37 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Gajanan Plaza in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
GAJANAN PLAZA1G+530 Dec 2021

Legal and disputes

What disputes are disclosed?

14 complaints are on the MahaRERA record for Gajanan Plaza, with orders passed in 14 of them.

14complaints

14with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005511801/07/2018PRASHANT SUKHADEV MAHAJAN vs Balaji construction companyorder passed
CC00600000019788404/08/2021PRASHANT SUKHADEV MAHAJAN vs Balaji Construction Coorder passed
CC00600000007948227/05/2019Mr. Jayantilal Parsotam Makwana vs Balaji Construction Co.order passed
CC00600000019277801/03/2020Balaji Construction Co. vs Principal Secretary, MahaRERA Authorityorder passed
CC00600000019470630/10/2020Jayantilal Purshottam Makwana vs Balaji Construction Companyorder passed
CC00600000019555207/01/2021Balaji Construction Co. vs Maharashtra Real Estate Regulatory Authorityorder passed
CC00600000019854809/10/2021Chintan Shah vs Balaji Construction Co.order passed
CC00600000019854909/10/2021Achala Patil vs M/s Balaji Construction Coorder passed
CC00600000019855009/10/2021Hetal Shah vs Balaji Construction Coorder passed
CC00600000019855109/10/2021Shashikumar Mishra vs M/s Balaji Construction Coorder passed
CC00600000019855209/10/2021Anjusha Kadam vs M/s Balaji Constuction Coorder passed
CC00600000019855409/10/2021Vikram Shah vs M/s Balalji Construction Coorder passed
CC00600000019855522/10/2021Achalal Patil vs M/s Balaji Construction Coorder passed
CC00600000042924314/02/2024Mukesh Soni vs BALAJI CONSTRUCTION COMPANYorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020To whom so ever it may concern this is to bring to your kind knowledge that we have been facing several problems due to which we are applying for extension of the project, the reas
30 Apr 202030 Apr 2020As per application and other supporting documents uploaded below. We are seeking extension under Section 5 read with Rule 6 of the RERA Act due to reasons set out in the Applicatio
30 Apr 202030 Jun 2021As per application dated 02/11/2020 uploaded in OTHER documents, specifically under Section 5 of MahaRERA Act read with Rule 6 of MahaRERA Rules.
30 Jun 202131 Dec 2027In view of the order of the Hon'ble MahaRERA Appellate Tribunal passed in the hearing held on 29/06/2021, we are making the present application as attached. The Regulatory Order Pa

Location, Land & Connectivity

Located at Mahavir nagar, 120 ft link road, 90ft poisur charkop rd, Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by 90 Ft DP Road, to the south by MHADA Property, to the east by 120 Ft DP Road and to the west by MHADA Property. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district24 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Balaji Construction Co. project & its RERA track record →

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

Gala Ares
possession by Dec 2029 · Square ONE Realty
Gala Avenue
possession by Dec 2027 · Morarji Gala & Sons
Gala Hub
declared completion Aug 2025 · Gala Comp
Galaxy Annnex
declared completion Dec 2025 · Galaxy Realtors
Galaxy Apartments CDF Wings
declared completion Jan 2021 · Housing Development AND Infrastructure L
Galaxy Aura
possession by Dec 2029 · Rudra Techno Construction Homes LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026