Mumbai/Project record

MahaRERA · the public record

Galaxy Emperia Phase-1

Boisar West · Galaxy Shine Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000017287

Delivery and registration

When is the project declared for completion?

Galaxy Emperia Phase-1 is registered with MahaRERA as P99000017287 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000017287
Registered on27 Jul 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Galaxy Emperia Phase-1 record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Galaxy Shine Developers is the promoter of record on 52 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

52projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Galaxy Emperia Phase-1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Building No-21G+531 Dec 2021
Building No-31G+431 Dec 2021
Building No-61G+431 Dec 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Galaxy Emperia Phase-1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000022071206/04/2022SUMEET SURESH PATHAK vs ASIF KHANorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023DUE TO COVID SLOWDOWN OF PROJECT
30 Dec 202331 Dec 2025Due to Covid ,non availabilty of material and labour.

Location, Land & Connectivity

Located at Boisar West, Navapur Road, Palghar, Palghar, 401501. Per the filed land record, the plot is bounded to the north by Survey no-8, to the south by Survey no-7 Pt, to the east by Survey No-7 Pt and to the west by Survey No-7 Pt. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Galaxy Emperia Phase-II
possession by Jun 2028 · Galaxy Shine Developers
Galaxy Garden - II
possession by Mar 2031 · Asian Builders And Developers
Galaxy Heights
possession by Dec 2027 · Shakti Developers
Galaxy Pride
possession by Jun 2027 · Gravity Developer
Galaxy Residency
possession by Dec 2026 · Mahashakti Enterprises
Galaxy Supreme
declared completion Jan 2026 · Gravity Developer

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026