MahaRERA · the public record

GANGADATTA RECIDENCY

CHAVDAR TALE · PRIYANKA PRASHANT GUJAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000012028

Delivery and registration

When is the project declared for completion?

GANGADATTA RECIDENCY is registered with MahaRERA as P52000012028 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000012028
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GANGADATTA RECIDENCY record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Priyanka Prashant Gujar is the promoter of record on 16 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GANGADATTA RECIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
GANGADATTA RESIDENCE C WING1G+431 Dec 2023
GANAGADATTA RECIDENCY B WING1G+531 Dec 2023
GANAGADATTA RECIDENCY A WING1G+631 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at CHAVDAR TALE, DONGRI POOL MAHAD BESIDE RAM MANDIR, Mahad, Raigarh, 402301. Per the filed land record, the plot is bounded to the north by CITY SURVEY NUMBER -1843 1844 1842, to the south by CITY SURVEY NUMBER -1847 1849, to the east by CITY SURVEY NUMBER -1833 and to the west by MUNICIPLE CORPORATION ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~120 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort113 km
Lower Parel / Worli business district120 km
Bandra Kurla Complex (BKC)124 km
Chhatrapati Shivaji Int'l Airport127 km
Powai / Hiranandani business park128 km
Andheri MIDC / SEEPZ130 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
Rukaiya Residence
possession by Dec 2026 · Vision Developers
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana

Other RERA-registered projects in Raigarh

Ganleela Apartment
declared completion Dec 2021 · Vishal Vimal Jain
Ganpat Arcade
declared completion Dec 2023 · Harikrishna Constructions
Ganushet Keni Heritage
declared completion Jun 2026 · Dinesh Manohar Keni
Ganushet Keni Heritage
possession by Jun 2027 · Dinesh Manohar Keni
Gardenia
declared completion Dec 2021 · M/S Kamdhenu Lifespaces
Gardenia
possession by Sep 2030 · Leela Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026