GHARKUL GRAVITY PHASE-I

NAHUR EAST · ANGATH PROPERTIES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800020569

Delivery and registration

When is the project declared for completion?

GHARKUL GRAVITY PHASE-I is registered with MahaRERA as P51800020569 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800020569
Registered on26 Apr 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GHARKUL GRAVITY PHASE-I record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Angath Properties Llp is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GHARKUL GRAVITY PHASE-I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+115.

BuildingWingsFloorsDeclared completion
SOUTHFIELD GRAVITY1G+11530 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for GHARKUL GRAVITY PHASE-I, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000036455727/03/2023Rajaram Gulabrao Khengre vs Angath Properties LLPorder passed

Location, Land & Connectivity

Located at NAHUR EAST, 90 FEET, Kurla, Mumbai Suburban, 400042. Per the filed land record, the plot is bounded to the north by CTS NO 731, to the south by 60 FEET ROAD, to the east by CTS NO 737 and to the west by 90 FEET ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Angath Properties LLP is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Angath Properties LLP

Angath Properties LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Kanjurmarg East

Bhandup Amol CHS LTD
possession by Dec 2026 · Sudhanshu Infrastructures Private Limite
Krystel By Kams Realtors
possession by Dec 2026 · Kams Realtors
Southfield Gravity
possession by Dec 2026 · Southfield Buildcon LLP
Shraddha Pavillion
possession by Jan 2027 · Shraddha Prime Projects Limited
Isha Vasyam
possession by Jun 2027 · Jyoti Sagar Corporation
Runwal Avenue Wing K
possession by Jun 2027 · Susneh Infrapark Private Limited

Major developers building in Kanjurmarg East

Other RERA-registered projects in Mumbai Suburban

Gharkul Height
declared completion Jun 2026 · Angath Properties LLP
Gharkul Latitude
declared completion Dec 2025 · Gharkul Developers
Ghatkopar Avenue Aaradhya ONE Earth Phase II
possession by Mar 2028 · MAN Realtors AND Holdings Private Limite
Ghatkopar Mahavir Palace
declared completion Dec 2017 · Pramod Mathurbhai Dhabaria
Ghatkopar Shilpakala CHS Limited
declared completion Dec 2022 · M/S SUN-VUB
Ghatkopar Tribhuvan Chsl
possession by Mar 2028 · Rajeshree Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.