MahaRERA Property Intelligence · Thane

GIRIRAJ DARSHAN

P51700050971 · Dombivali · promoter Giriraj Darshan

Certificate SignedDue 30 Dec 2024

Delivery & Registration

MahaRERA registrationP51700050971
Registered on16 May 2023
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Giriraj Darshan is the promoter of record on 26 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~80.0% of the estimated project cost incurred as of the last certificate (₹4.40 Cr spent against a ₹5.50 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~80.0% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 6 homes filed with MahaRERA, 0 are sold/booked and 6 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101737 sqft (68.49 sqm)-
Floor 1102345 sqft (32.05 sqm)-
Floor 1103593 sqft (55.06 sqm)-
Ground/Floor 0Shop 1441 sqft (41 sqm)-
Ground/Floor 0Shop 2277 sqft (25.73 sqm)-
Ground/Floor 0Shop 3238 sqft (22.08 sqm)-

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 6 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
11G+5631 Dec 2023

Unit mix on the filing: 6 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202330 Dec 2024It has become difficult for us as builders and developers to complete the project in the declared selling price, as the cost of construction has been increasing day by day. We are

Location, Land & Connectivity

Located at Dombivali, Golivali , Kalyan, Thane, 421203. Per the filed land record, the plot is bounded to the north by S No 24, to the south by S No 27, to the east by S No 25 and to the west by S No 14. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Hedutane

Fiora F
possession by Aug 2026 · Lodha Developers Limited
Liana D
possession by Aug 2026 · Lodha Developers Limited
Ambrin 3
possession by Sep 2026 · Impressions
Liana C
possession by Sep 2026 · Lodha Developers Limited
Casa Belvedere
possession by Oct 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Hedutane

Other RERA-registered projects in Thane

Giriraj Dreams, THE State Bank OF India Employees Cooperative Housing Society LTD
declared completion Dec 2023 · Pridedream Realtors Private Limited
Giriraj Jewel
declared completion Dec 2023 · Grandeur Developers LLP
Giriraj Sparsh
declared completion Jun 2025 · Dura Vida Associates
Giriraj Swastik 15-16 Wing A
possession by Dec 2028 · M/s. Shubham Developers
Girivihar
declared completion May 2019 · Abhinandan Enterprise
Girnar Tirth
declared completion Jun 2019 · Parshwa Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026