Mumbai/Project record

MahaRERA · the public record

GOKUL GRAND - 1, 2 & 3

PALGHAR WEST · MANGALAM ENTERPRISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

4units filed as unsoldInventory · 16 September 2026
31 May 2026declared completionMahaRERA registration · read 12 Jul 2026
82registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000006400

Delivery and registration

When is the project declared for completion?

GOKUL GRAND - 1, 2 & 3 is registered with MahaRERA as P99000006400 and the promoter has declared completion for 31 May 2026.

31 May 2026

declared completion

4months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000006400
Registered on14 Aug 2017
Promoter-declared completion31 May 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOKUL GRAND - 1, 2 & 3 record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Mangalam Enterprise is the promoter of record on 32 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

32projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In GOKUL GRAND - 1, 2 & 3, 78 of 82 homes filed with MahaRERA are recorded as sold or booked (63 with registered agreements and 15 booked), about 95%, and 4 remain available.

95%sold

78 of 82 homes

₹15.23 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹10.95 Cr (about 72%) is recorded as collected and ₹4.27 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 78 registered agreements, the effective carpet rate is ₹5,808/sqft, with eight in ten falling between ₹5,198 and ₹12,124 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101311 sqft (28.9 sqm)₹19.60 Lakh
Floor 1104437 sqft (40.58 sqm)₹34.57 Lakh
Floor 1105311 sqft (28.9 sqm)₹17.26 Lakh
Ground/Floor 04107 sqft (9.97 sqm)₹9.00 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 78 homes carry one, and 4 of the 82 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
101311 sqftRs 16.55 lakh typical, over Rs 16.52 lakh to Rs 18.67 lakh3 filed on this stack, floors 2–4

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In GOKUL GRAND - 1, 2 & 3, every one of the 4 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 3 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 82 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GOKUL GRAND-21G+42817 Dec 2021
GOKUL GRAND-31G+42817 Dec 2021
GOKUL GRAND-41G+42617 Dec 2021

Unit mix on the filing: 68 residential and 14 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for GOKUL GRAND - 1, 2 & 3, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019534711/01/2021Sanjay Shah vs Mangalam Enterprisesorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.

FromExtended toStated reason
as registered18 Dec 2020Being a project with three big buildings, we under-estimated the time for completion of project & hence did not gave enough duration while registering. Even after that works were h
18 Dec 202030 Jun 2023Back to back lockdown in two consecutive years led to complete blunder of all project planning. Recovery time after the lockdown also affects the work progress along with the obvio
30 Jun 202331 May 2024Work was stopped as we were applied for additional FSI. But we withdraw the same and now started the work once again.
31 May 202431 May 2025due to labour and material isuue
31 May 202531 May 2026Project was delayed due to local issued at the site but now the works are on the right track & will be completed in this year after which OC application process will take few month

Location, Land & Connectivity

Located at PALGHAR WEST, MAHIM ROAD, Vasai, Palghar, 401404. Per the filed land record, the plot is bounded to the north by INTERNAL ROAD, to the south by 9 M LAYOUT ROAD, to the east by PLOT NO-16 AND 17 and to the west by PLOT NO-14. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~62 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ62 km
Powai / Hiranandani business park64 km
Chhatrapati Shivaji Int'l Airport66 km
Bandra Kurla Complex (BKC)69 km
Lower Parel / Worli business district76 km
Nariman Point / Fort84 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mangalam Enterprise is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Gokul Hari Ananta
possession by Dec 2030 · Mehta Ventures
Gokul Heights
possession by Dec 2027 · Gokul Infra
Gokul Mathura Heights
possession by Dec 2030 · Thakkar Construire LLP
Gokul Nagar
possession by Dec 2026 · Fivestar Realtors
Gokul Nakshatra
possession by Dec 2027 · JSB Homemakers Private Limited
Gokul Nakshatra II
possession by Dec 2029 · JSB Homemakers Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026