Mumbai/Project record

MahaRERA · the public record

GOKUL VILLA

SHAHAPUR · GREENCITY INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700030166

Delivery and registration

When is the project declared for completion?

GOKUL VILLA is registered with MahaRERA as P51700030166 and the promoter has declared completion for 01 Jun 2023.

01 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700030166
Registered on05 Aug 2021
Promoter-declared completion01 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOKUL VILLA record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Greencity Infra is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In GOKUL VILLA, 7 of 19 plots filed with MahaRERA are recorded as sold or booked, about 37%, and 12 remain available.

37%sold

7 of 19 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GOKUL VILLA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SHAHAPUR, SARANGPURI, Thane, Thane, 421601. Per the filed land record, the plot is bounded to the north by SNO 39, to the south by ROAD TO SARANGPURI VILLAGE, to the east by SNO 65 and to the west by SNO 38. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Gokuldham
possession by Dec 2028 · Maanit Infra
Gold Crest
possession by May 2027 · Jay Ganesh Developers
Goldcrest Residency - Phase 1
declared completion Dec 2020 · Savita Homemakers LLP
Goldcrest Residency - Phase 2
possession by Mar 2027 · Savita Homemakers LLP
Golden City
possession by Dec 2026 · Krishna Infra
Golden Heights
possession by Dec 2027 · Jainam Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026