Mumbai/Project record

MahaRERA · the public record

GOKULDHAM ZONE 2

Boisar · RAJ SHREE NIRMAN BUIDERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Oct 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000012100

Delivery and registration

When is the project declared for completion?

GOKULDHAM ZONE 2 is registered with MahaRERA as P99000012100 and the promoter has declared completion for 31 Oct 2018.

31 Oct 2018

declared completion

95months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000012100
Registered on01 Sep 2017
Promoter-declared completion31 Oct 2018
Current statusCertificate Signed
Against todayabout 95 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOKULDHAM ZONE 2 record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Raj Shree Nirman is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GOKULDHAM ZONE 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
WING H1G+5-
WING I1G+531 Oct 2018
WING J1G+531 Oct 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for GOKULDHAM ZONE 2, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000025144727/06/2022Rajendra Prasad Verma vs Shri Ajaay R. Sharmaaorder passed

Location, Land & Connectivity

Located at Boisar, Thane, Thane, 401501. Per the filed land record, the plot is bounded to the north by R G, to the south by LAYOUT ROAD, to the east by R G and to the west by BUILDING NO 8 AB WING. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Golden Bliss
possession by Dec 2027 · Mahalaxmi Homes
Golden Enclave
possession by Dec 2026 · Golden Realty
Golden Heights
declared completion Jul 2022 · Golden Group AND Developers
Golden Paradise
possession by Dec 2027 · Devendra Rishimuni Gupta
Golden Villa
possession by Dec 2031 · OM JAI Kavish Realtors
Gopal Niwas
declared completion Jun 2022 · Jay Gopal Group Builder

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026