Mumbai/Project record

MahaRERA · the public record

HANIF PLAZA

VAHOOR · YATHAVAN ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000021969

Delivery and registration

When is the project declared for completion?

HANIF PLAZA is registered with MahaRERA as P52000021969 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000021969
Registered on25 Aug 2019
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HANIF PLAZA record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HANIF PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
HANIF PLAZA A WING1G+431 Dec 2022
HANIF PLAZA B WING1G+431 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VAHOOR, VAHOOR, Thane, Thane, 402301. Per the filed land record, the plot is bounded to the north by HANIF ISANE REMAINING LAND, to the south by S NO 33 HISSA NUMBER 1B, to the east by SMALL RIVER and to the west by S NO 33 HISSA NUMBER 1 B. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
Rukaiya Residence
possession by Dec 2026 · Vision Developers
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana

Other RERA-registered projects in Raigarh

Hanisha Residency
declared completion May 2026 · Gurudarshan Realtors
Happy Home
declared completion Dec 2024 · Happy Leisure Realties LLP
Happy Homes
possession by Mar 2027 · Ratneshwar Developers
Happy Homes
declared completion Mar 2026 · Harjinder Kaur Charandeep Singh
Harbour City Sector-I
declared completion Mar 2018 · Garva Land Deal Private Limited
Harbour City Sector-III
declared completion Mar 2019 · Garva Land Deal Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026