MahaRERA Property Intelligence · Thane

Hari Krupa Residency, Kharde, Shahapur

P51700010244 · KHARDI · promoter Harikrupa Buildcon Llp

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP51700010244
Registered on24 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Harikrupa Buildcon Llp is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A TYPE BUILDING WING-A1G+731 Jul 2022
A TYPE BUILDING WING-B1G+731 Jul 2022
D TYPE WING -C1-31 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KHARDI, KHARDI, Kurla, Mumbai Suburban, 421601. Per the filed land record, the plot is bounded to the north by D P Road, to the south by AdjoiningSurvey 159, to the east by Survey No 159 and to the west by Open Plot Survey 162A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~73 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park73 km
Andheri MIDC / SEEPZ74 km
Chhatrapati Shivaji Int'l Airport78 km
Bandra Kurla Complex (BKC)79 km
Lower Parel / Worli business district88 km
Nariman Point / Fort94 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Vaishnavi Dham Complex
possession by Jul 2026 · Vaishnavi Builders AND Developers
UMA Residency, Phase I
possession by Aug 2026 · Adarsh Infra Developers
Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
SAI Palace
possession by Oct 2026 · Vardhaman Developers
Sava Arcade
possession by Oct 2026 · Sava Developers

Major developers building in Shahapur

Other RERA-registered projects in Thane

Hari OM Arcade
declared completion Feb 2021 · Ideal Enterprises
Hari Sanskruti
declared completion Jun 2026 · Saraswati Developers
Hari Shrushti
declared completion Dec 2022 · Shiv Shakti Developers
Hari Shrushti
possession by Dec 2027 · Shrushti Creators
Hari Vijay Lawns Building No.2
declared completion Dec 2022 · Creative Construction
Harihar Darshan
possession by Dec 2026 · Borgaonkar Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026