MahaRERA Property Intelligence · Thane

HERAMB PARK PHASE II

P51700004551 · promoter Sai Samruddhi Construction

Certificate SignedDue 31 Jul 2019

Delivery & Registration

MahaRERA registrationP51700004551
Registered on09 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sai Samruddhi Construction is the promoter of record on 94 projects, of which 14 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
E - WING1G+831 Jul 2019
F - WING1G+831 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by LAND BEARING GUT NO 65, to the south by LAND BEARING GUT NO 62, to the east by LAND BEARING 12 MTR WIDE EXST RD GUT NO 61 H 2P and to the west by GUT NO 76. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~36 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park36 km
Andheri MIDC / SEEPZ39 km
Chhatrapati Shivaji Int'l Airport41 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district48 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Herambh Hights
possession by Mar 2029 · Varad Infra
Herambkrupa C H S LTD
declared completion Feb 2020 · Shree SAI Builders & Developers
Herbelia
declared completion Dec 2023 · Acme Housing India Private Limited
Heritage
declared completion May 2024 · Shree SAI Developers
Heritage Garden
declared completion Jun 2025 · Shanti Builders & Developers
Heritage Heights
declared completion Dec 2024 · Shanti Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026