Mumbai/Project record

MahaRERA · the public record

HERITAGE AHURA RESIDENCY

Ghatkopar west · KERSI JAMSHED RANDERIA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

97units filed as unsoldInventory · 13 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
251registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009207

Delivery and registration

When is the project declared for completion?

HERITAGE AHURA RESIDENCY is registered with MahaRERA as P51800009207 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009207
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HERITAGE AHURA RESIDENCY record 39 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Construction

How much construction cost has been reported?

In HERITAGE AHURA RESIDENCY, ₹11.67 Cr of a declared ₹49.81 Cr estimated project cost is reported as incurred, about 23.4%, as at the last certified filing with MahaRERA.

23.4%

₹11.67 Cr

of ₹49.81 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In HERITAGE AHURA RESIDENCY, 16 of 113 homes filed with MahaRERA are recorded as sold or booked, about 14%, and 97 remain available.

14%sold

16 of 113 homes

₹19.23 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹9.77 Cr (about 51%) is recorded as collected and ₹9.46 Cr as receivable. The project registers 251 homes in total, while this sold/unsold inventory filing covers 113 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 16 registered agreements, the effective carpet rate is ₹12,190/sqft, with eight in ten falling between ₹10,539 and ₹17,273 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 6 reserved.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 16 homes carry one, and 97 of the 119 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1002960 sqftRs 11,476 a sq ft typical, over Rs 10,337 to Rs 14,5025 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In HERITAGE AHURA RESIDENCY, 30 of the 97 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 96 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 251 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
WING A REHAB1G+769-
WING C SALE1G+1245-
WING E SALE1G+1224-
WING D SALE1G+1244-
WING B REHAB1G+869-

Unit mix on the filing: 229 residential and 22 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

8 complaints are on the MahaRERA record for HERITAGE AHURA RESIDENCY, with orders passed in 8 of them.

8complaints

8with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020973224/01/2022Poonam Sandeep Jain vs Heritage Housing Corporationorder passed
CC00600000020973924/01/2022Sandeep R. Jain vs Heritage Housing Corporationorder passed
CC00600000020974024/01/2022Mithalal Duggad vs Heritage Housing Corporationorder passed
CC00600000020974124/01/2022Ghwarchand m. Jain Bafna vs Heritage Housing Corporationorder passed
CC00600000020974324/01/2022Dipika Poonamchand Jain vs Heritage Housing Corporationorder passed
CC00600000020974524/01/2022Nitin Kumar Virdichand Nahar vs Heritage Housing Corporationorder passed
CC00600000021055131/03/2022DILIP PHOOLCHAND JAIN vs heritageCorporation & Anr.order passed
CC1250106830/03/2025MRS REKHA DEEPAK SHAH vs KERSI JAMSHED RANDERIAorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2023As per the attachment
29 Dec 202331 Dec 2028As per attachment

Location, Land & Connectivity

Located at Ghatkopar west , Mazda house Behind C.I.D office L.B.S MARG , Kurla, Mumbai Suburban, 400086. Per the filed land record, the plot is bounded to the north by ANDHERI GHATKOPAR LINK ROAD, to the south by LBS ROAD, to the east by SARVODAYA SCHOOL and to the west by MANGAL BHAVAN BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district12 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar West

O AND S Royale
possession by Dec 2026 · Suchita Orange Project Royale
Sarvonnati CHS LTD
Deregistered by MahaRERA · possession by Dec 2026 · JAI Enterprises
Vighneshwar Cooperative Housing Society Limited
possession by Dec 2026 · Vighneshwar Coop Housing Society Limited
Arihant Heights
possession by Dec 2026 · Arihant Infrastructure Company
Avani Signature
possession by Dec 2026 · Avani Buildcon
Sanghvi Parsssva Jivdaya
possession by Dec 2026 · Sanghvi Constructions

Other RERA-registered projects in Mumbai Suburban

Heritage Lakeside
possession by Dec 2031 · Heritage Lifestyles LLP
Heritage Signature
declared completion Mar 2026 · Heritage Homes
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
Hetali Souk
possession by Jul 2029 · Jayesh H. Pandya, Bhavna J. Pandya, And
Hicons Corporate Lounge
declared completion Dec 2022 · Tejal Minerals AND Grinders PVT LTD
Highland A B C D AND E Wing
possession by Dec 2026 · HGP Community Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026