MahaRERA Property Intelligence · Thane

HEVA APARTMENT

P51700017086 · SHAHPUR · promoter Hub Realtor

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP51700017086
Registered on11 Jul 2018
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
HEVA APARTMENT1G+730 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SHAHPUR, ATGAON, Mumbai, Mumbai Suburban, 421601. Per the filed land record, the plot is bounded to the north by SURVEY NO 189, to the south by SURVEY NO 33 H NO 6, to the east by ROAD and to the west by RAILWAY BOUNDARY LINE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Vaishnavi Dham Complex
possession by Jul 2026 · Vaishnavi Builders AND Developers
UMA Residency, Phase I
possession by Aug 2026 · Adarsh Infra Developers
Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
SAI Palace
possession by Oct 2026 · Vardhaman Developers
Sava Arcade
possession by Oct 2026 · Sava Developers

Major developers building in Shahapur

Other RERA-registered projects in Thane

HG- A1
possession by Dec 2029 · Siddhi Real Estate Developers
Hibiscus Heights
declared completion Jun 2024 · Mohan Dinesh Singh
Highland Haven Building 1A DEW-B Phase 1
declared completion Mar 2019 · Siddhi Krish Developers
Highland Haven Building 2B DEW-A Phase 2
declared completion Mar 2019 · Siddhi Krish Developers
Highland Haven Building 3C Coral-B Phase 3
declared completion Mar 2019 · Siddhi Krish Developers
Highland Haven Building 4D Coral-A Phase 4
declared completion Mar 2019 · Siddhi Krish Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026