MahaRERA Property Intelligence · Raigarh

HILL VIEW RESIDENCY

P52000017907 · MAMDAPUR · promoter Mcbool Realtors

Certificate SignedDue 31 Jul 2024

Delivery & Registration

MahaRERA registrationP52000017907
Registered on25 Sep 2018
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
HILL VIEW RESIDENCY1G+631 Aug 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201931 Jul 2023Due to Pandemic there was scarcity of labour and the work was delayed and minute works are yet to be completed.
31 Dec 201931 Dec 2022Since our project is at a remote place, we had face hardship due to both the lockdowns. Further due to pandemic our previous contractor was not able to arrange man power.
31 Dec 201930 Dec 2020DELAY IN MATERIALAVAILABILITY
31 Dec 201931 Jul 2024Delay was cause because of labour shortage and inappropriate planning and execution made by sub contractor.

Location, Land & Connectivity

Located at MAMDAPUR, -, Kurla, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by S NO 160, to the south by 7 5 M ROAD, to the east by PLOT NO 26 and to the west by PLOT NO 28. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~43 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park43 km
Bandra Kurla Complex (BKC)46 km
Chhatrapati Shivaji Int'l Airport46 km
Andheri MIDC / SEEPZ47 km
Lower Parel / Worli business district50 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

SAI Krupa Valley- Phase 1
possession by Aug 2026 · SAI Krupa Developers
Noble Apartment
possession by Aug 2026 · Asra Reality
Madina Complex
possession by Aug 2026 · Al-Hamd Developers
Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Aliza Apartments
possession by Dec 2026 · M/S SKY Homes

Major developers building in Neral

Other RERA-registered projects in Raigarh

Hill View Residency
declared completion Jun 2021 · Shree Siddhivinayak Builders & Devel
Hillcrest
possession by Dec 2027 · Erdamor Realty LLP
Hillcrest Apartment
declared completion Dec 2024 · Seahjad Ahmed Siddiqui
Hills Paradise
possession by Mar 2027 · Bhuvanesh Dhondibhau Jagdale
Hills Regency
declared completion Dec 2019 · Tech Nova Enterprises
Hills Residency
declared completion Jun 2018 · RAJ Homes S V Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026