MahaRERA Property Intelligence · Thane

HIRALAXMI APARTMENT

P51700010317 · KADVA GALI · promoter Shree Sadguru Developers

Certificate SignedDue 30 Oct 2023

Delivery & Registration

MahaRERA registrationP51700010317
Registered on24 Aug 2017
Promoter-declared completion30 Oct 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Sadguru Developers is the promoter of record on 114 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
HIRALAXMI1G+829 Oct 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202331 Oct 2022Due to lock-down and Covid-19 situation we were unable to complete the work, also we recently received CC for the further work dated 04-05-2021. So kindly give us an extension till
30 Oct 202329 Oct 2020DELAY OF SIX MONTHS TO ISSUE PLINTH CERTIFICATE BY TMC. 70% WORK DONE
30 Oct 202330 Oct 20231. Due to Pandemic work has been held-up completely for one and half year. 2. Some flats and 1 Commercial unit worth ₹. 3.47 Crore remain unsold due to which work completion get

Location, Land & Connectivity

Located at KADVA GALI, 9. 00 M. W. DP. RD, Thane, Thane, 400601. Per the filed land record, the plot is bounded to the north by SURVEY NO 165 SHANBAG, to the south by SURVEY NO 168 MAHAVIR TRADING, to the east by SURVEY NO 183 and to the west by ROAD KADVA GALI. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park12 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Sadguru Developers is the promoter on 9 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Shree Sadguru Developers project & its RERA track record →

Other RERA-registered projects in Thane

Nandigram
possession by Jul 2026 · Yogesh Kishor Mahajan
Embassy One Thane - 1A 1B 1C
possession by Aug 2026 · Tapir Constructions Limited
Aurum
possession by Sep 2026 · Shree GHP Housing
Avesa
possession by Oct 2026 · Jagdale Infrastructure Pvt. Ltd.
Ramashankar CHS LTD
possession by Oct 2026 · SAI Prasad Builders AND Developers
Bhavana Apartment CHS
possession by Nov 2026 · Shree Infra

Major developers building in Thane

Other RERA-registered projects in Thane

Hiranandani Westgate - Hampstead
possession by Dec 2032 · Shoden Developers Private Limited
Hiranandani Westgate Phase 1
possession by Oct 2031 · Shoden Developers Private Limited
Hiranandani Woodspring Bldg A-Oakwood Bldg B-Bridgewood Bldg C-Greenwood
possession by Jan 2028 · Golden Mile Builders LLP
Hitech Park
possession by Dec 2029 · Silverleaf Buildcon
Hiya Avenue
possession by Mar 2029 · Vinod Lalchandji Mehta
Hiya Heights
declared completion Mar 2024 · Vinod Lalchandji Mehta

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026