Mumbai/Project record

MahaRERA · the public record

HORIZON

ALIBAG · MANDAR ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000025775

Delivery and registration

When is the project declared for completion?

HORIZON is registered with MahaRERA as P52000025775 and the promoter has declared completion for 31 Mar 2022.

31 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000025775
Registered on14 Jul 2020
Promoter-declared completion31 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HORIZON record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mandar Enterprises is the promoter of record on 22 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HORIZON in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
HORIZON1G+330 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2022DUE TO CORONA PANDEMIC WE COULD NOT COMPLETE WORK ON TIME

Location, Land & Connectivity

Located at ALIBAG, Shreebag No. 3, Chendhare, Alibag, Raigarh, 402201. Per the filed land record, the plot is bounded to the north by MUNICIPAL ROAD, to the south by MUNICIPAL GUTTER, to the east by PLOT NO R33 and to the west by PLOT NO R35. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mandar Enterprises is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Mandar Enterprises

Mandar Enterprises
Past its declared completion dateRaigarh
Mandar Enterprises
FlaggedRaigarh

Other RERA-registered projects in Alibag

Excellensea Villas Project
possession by Dec 2026 · Unicorp Realty Private Limited
Balibaug Rekreasi
possession by Dec 2026 · Pushpam Infra LLP
Lakshminarayan CO-OP Housing Society LTD Proposed
possession by Dec 2026 · Elnube Realtors PVT LTD
Swastik Orchid
possession by Dec 2026 · Swastik Developers
Savitri Heritage
possession by Mar 2027 · Mukesh Bhoormal Jain
Shree Radha Krishna Residency
possession by May 2027 · Shree Radha Enterprises

Major developers building in Alibag

Other RERA-registered projects in Raigarh

Horizon Landmark
possession by Dec 2030 · Greenscape Kalpana Struct CON
Hrishikesh 3
declared completion Oct 2025 · Rare Livspace
Hrishikesh Elite
possession by Dec 2026 · Hrishikesh Group
Hrishikesh Palm
possession by Dec 2027 · Hrishikesh Group
Ideal Palace
declared completion Jun 2026 · Infinity Enterprises
Ideal Residency
possession by Dec 2030 · Ideal Builders & Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026