30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800028166

Delivery and registration

When is the project declared for completion?

INSIGNIA is registered with MahaRERA as P51800028166 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800028166
Registered on10 Feb 2021
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INSIGNIA record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shreepati Rise Estate is the promoter of record on 13 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for INSIGNIA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
INSIGNIA1G+1630 Jun 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Of Mumbai1442017No Adverse Order Passed
City Civil Dindoshi2192015No Adverse Order Passed
High Court Of Mumbai12012020No Adverse Order Passed
City Civil Dindoshi18092019No Adverse Order Passed
High Court Of Mumbai21612019No Adverse Order Passed

Location, Land & Connectivity

Located at VILE PARLE (WEST), OLD POLICE STATION ROAD, Mumbai City, Mumbai City, 400056. Per the filed land record, the plot is bounded to the north by OLD POLICE STATION, to the south by SHALIMAR BLDG AND NEEL SHEEL PREMISES CSL, to the east by SAROJINI ROAD and to the west by PUBLIC ROAD KNOWN AS PAILANE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreepati Rise Estate LLP is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shreepati Rise Estate LLP

Shreepati Rise Estate LLP
FlaggedMumbai Suburban
Shreepati Rise Estate LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Vile Parle West

Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP
Meera Kunj
possession by Dec 2026 · Arham Realty

Other RERA-registered projects in Mumbai Suburban

Insignia
possession by Dec 2026 · Two Taurus Realty LLP
Inspira Aura
possession by Mar 2029 · IR JPV Estates Pvt. Ltd.
Inspira ONE
possession by Jun 2030 · Inspira Buildcon Private Limited
Inspire Residency
possession by Dec 2026 · Sardar Realty
Integrated Ahana
declared completion Apr 2025 · Integrated Spaces Limited
Integrated Arcade
declared completion Mar 2026 · Sadgurukrupa Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.