Ishwari Heights

Vishnunagar, Dombivli West. · Vinay Arun Surve

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700045739

Delivery and registration

When is the project declared for completion?

Ishwari Heights is registered with MahaRERA as P51700045739 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700045739
Registered on06 Jun 2022
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ishwari Heights record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ishwari Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
ISHWARI HEIGHTS1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024A sanction for an additional floor was received on 18th January 2024 due to additional TDR purchased and UDCPR. Therefore, we request you to grant an extension till December 31, 20
31 Dec 202430 Jun 2025The project experienced a delay due to the issuance of a revised commencement certificate in January 2024. This revised certificate sanctioned additional construction, requiring ad

Location, Land & Connectivity

Located at Vishnunagar, Dombivli West. , M. Karve Road, Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by 12 WIDE ROAD, to the south by CTS NO 1286 VARSHA CHS, to the east by CTS NO 1288 and to the west by CTS NO 2291 JAYESH KRUPA CHS. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli West

Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO
Chintamani Heights & Chintamani Kuber
possession by Dec 2026 · Chintamani Developers
Indira Galaxy
possession by Dec 2026 · Shree Developers
Jai Shree Ganesh Co-Operative Housing Society Limited
possession by Dec 2026 · Shree Vyankatesh Enterprises

Major developers building in Dombivli West

Other RERA-registered projects in Thane

Iskcon Residency Phase 1
declared completion Dec 2025 · Iskcon Realtors
Iskcon Residency Phase-II Type A
possession by Dec 2030 · Iskcon Realtors
Iskcon Residency Phase-II Type B
possession by Dec 2029 · Iskcon Realtors
J D Palms
possession by Mar 2027 · J D Housing LLP
J K Kasturi
declared completion Dec 2024 · J.k.infra
Jacqueline Apartment CO-Operative Housing Society LTD
possession by Apr 2028 · High Leap

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026