MahaRERA · the public record
JAANBAI KRUPA
VILLAGE NAVALI · KALUBHAI RAMJIBHAI GAJERA
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2024
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P99000024101
Delivery and registration
When is the project declared for completion?
JAANBAI KRUPA is registered with MahaRERA as P99000024101 and the promoter has declared completion for 31 Dec 2024.
31 Dec 2024
declared completion
21months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P99000024101 |
| Registered on | 20 Jan 2020 |
| Promoter-declared completion | 31 Dec 2024 |
| Current status | Certificate Signed |
| Against today | about 21 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JAANBAI KRUPA record 20 quarterly progress reports since registration.
20quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Kalubhai Ramjibhai Gajera is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
2projects
registered with MahaRERA
1flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for JAANBAI KRUPA in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| JAANBAI KRUPA - A WING | 1 | G+5 | - |
| JAANBAI KRUPA - B WING | 1 | G+5 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2024 | After Corona Virus effect supply of Material and Labour Contractor is affected hence work progress is getting slow |
Location, Land & Connectivity
Located at VILLAGE NAVALI, PLOT NO 5 6 AND 11 S NO 27/2/1, Mumbai, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by PLOT NO 4, to the south by 12 MTR ROAD, to the east by 18 MTR ROAD and to the west by PLOT NO 12. These are the boundaries as recorded in the filed land record.