Mumbai/Project record

MahaRERA · the public record

Jangid Trinity

Borivali East · Jangid Construction P LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

33units filed as unsoldInventory · 19 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
332registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800051923

Delivery and registration

When is the project declared for completion?

Jangid Trinity is registered with MahaRERA as P51800051923 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800051923
Registered on13 Jul 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Jangid Trinity record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Jangid Construction Ltd is the promoter of record on 12 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Jangid Trinity, ₹123.56 Cr of a declared ₹450.00 Cr estimated project cost is reported as incurred, about 27.5%, as at the last certified filing with MahaRERA.

27.5%

₹123.56 Cr

of ₹450.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Jangid Trinity, 281 of 332 homes filed with MahaRERA are recorded as sold or booked (122 with registered agreements and 159 booked), about 85%, and 51 remain available.

85%sold

281 of 332 homes

₹627.33 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹283.73 Cr (about 45%) is recorded as collected and ₹343.67 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 281 registered agreements, the effective carpet rate is ₹20,539/sqft, with eight in ten falling between ₹18,000 and ₹24,600 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 299 homes carry one, and 33 of the 332 are recorded unsold. Since we started watching this ledger, 33 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
Jangid Trinity - 39041,206 sqftRs 2.5236 cr typical, over Rs 1.8693 cr to Rs 3.2562 cr199 filed on this stack, floors 1–42

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Jangid Trinity, every one of the 33 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 32 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 332 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
sale building no 41G+16332-

Unit mix on the filing: 332 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Borivali East, Siddhartha Nagar, Thane, Thane, 400066. Per the filed land record, the plot is bounded to the north by CTS NO 180 181 AND 182B, to the south by CTS NO 170 171 172 PORTION OF CTS NO 179A, to the east by CTS NO 179B and to the west by CTS NO 173 175 177 AND W E HIGHWAY. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Janki Heritage
declared completion Dec 2025 · Heritage Lifestyles & Developers Pvt
Jasoda Chsl-Aryaman Metropolis
declared completion Jul 2022 · Matra Realty And Developers Ltd
Jaswanti Jewel
possession by Dec 2027 · Paradise Construction Company
Jaswanti Square
possession by Dec 2028 · Not Available
JAY Ashapura Chsl
possession by Dec 2027 · Sumukha Developers
Jay Celestial Redevelopment Vidharbha CHS Ltd
declared completion Jun 2024 · JAY Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026