Mumbai/Project record

MahaRERA · the public record

Jay Shreenath Niwas CHS Ltd

Kandivali West · Shree Sai Consultants

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800004474

Delivery and registration

When is the project declared for completion?

Jay Shreenath Niwas CHS Ltd is registered with MahaRERA as P51800004474 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800004474
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Jay Shreenath Niwas CHS Ltd record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shree Sai Consultants is the promoter of record on 25 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

25projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Jay Shreenath Niwas CHS Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Shreenath Apartment1G+1731 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020I Mr. Jayesh Tanna,say that, due to some issues which aroused with the society as well as due to change in permission related norms where in MHADA became the planning authority, ge
31 Dec 202031 Dec 2020To, MAHARERA Authorities Mumbai. Subject: Request for extension of timeline in respect of completion of the project. Sir/Madam, This is to bring to your kind attention initia
31 Dec 202031 Dec 2022Due to changes in the MHADA policy all the MHADA redevelopment projects were stalled for a period of 7-8 years. The same is conveyed in the letter addressed by MHADA VP dated 27.4.

Location, Land & Connectivity

Located at Kandivali West, Shantilal Modi Road, Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by Habib-bhi Road, to the south by Plot No 38A, to the east by Plot No 36 and to the west by Plot No 40. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

Jayakunj Apartment Chsl
declared completion Oct 2022 · Jayakunj Apartment Chsl
Jaydeep AND Gami Evara
possession by Dec 2028 · M/S Real Infrastructure CO
Jaydeep Mark
possession by Dec 2027 · Jaydeep Realspace LLP
Jaydeep ONE
possession by Mar 2029 · Trinity Creative Homes LLP
Jayhari CHS LTD
declared completion Dec 2025 · DAM Builders AND Developers
Jaykant Bliss
possession by Dec 2026 · Chitalia Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026