MahaRERA Property Intelligence · Palghar

Jayvant Srushti

P99000078188 · 0 · promoter Shree Shailam Developers

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationP99000078188
Registered on29 Nov 2024
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Building no 2 Type 31G+2-
Building no 2 Type 41G+2-
Building no 3 Type 31G+2-
Building no 3 Type 41G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at 0, 0, Palghar, Palghar, 401402. Per the filed land record, the plot is bounded to the north by Land of Jyotsna Jayvant Patil, to the south by Grampanchayat Road, to the east by Land of Padmavaati Parshuram Mhatre and to the west by Land of Shridhar Nanaji Raut. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Sanmukh Sunshine
Not filing quarterly progress reports · possession by Oct 2026 · Sanmukh Realty LLP
Bafna Luxuria
possession by Dec 2026 · Shrushti Developers
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Shakti Industrial Estate
Not filing quarterly progress reports · possession by Dec 2026 · Shakti Krupa Developers
Star Signature City - Star Pearl
possession by Dec 2026 · Star Builders & Developers

Other RERA-registered projects in Palghar

JB Enterprises
declared completion Dec 2025 · Raju Bherulal Jain
JB Pearl
declared completion Mar 2026 · JB Developers
JB Solitaire
possession by Jan 2030 · Rajhans Realtors
Jeevika Heights
possession by Dec 2026 · Fia Developers Pvt. Ltd.
JEM Emerald
possession by Mar 2028 · JEM Infra-Build LLP
Jinal Industrial Estate
declared completion Dec 2023 · Richa Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026