Mumbai/Project record

MahaRERA · the public record

JIVDANI MAULI

Virar East · Kiran Ramesh Patil

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000048315

Delivery and registration

When is the project declared for completion?

JIVDANI MAULI is registered with MahaRERA as P99000048315 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000048315
Registered on26 Dec 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JIVDANI MAULI record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Kiran Ramesh Patil is the promoter of record on 177 projects registered with MahaRERA, 29 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

177projects

registered with MahaRERA

29flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JIVDANI MAULI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
JIVDANI MAULI A AND B WING1G+2631 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Virar East, Sai Nath Nagar, Chandansar Road, Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by Jivdani Chhaya, to the south by Shankar mandir, to the east by Shivshakti Apartment and to the west by Shree Sai Sawali Apartment. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~39 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ39 km
Powai / Hiranandani business park40 km
Chhatrapati Shivaji Int'l Airport43 km
Bandra Kurla Complex (BKC)46 km
Lower Parel / Worli business district53 km
Nariman Point / Fort61 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Radheya Enterprises
possession by Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
possession by Dec 2026 · VED Ganga
SAI Prasad Apartment
Not filing quarterly progress reports · possession by Dec 2026 · Vinod Motiram Pawar

Other RERA-registered projects in Palghar

Jivdani Plaza
declared completion May 2023 · Milind Shridhar Surve
Jivdani Pride
possession by Dec 2029 · Jivdani Krupa Builders & Developers
Jivdani Residency
declared completion Dec 2024 · Vinay Harihar Singh
Jivdani Shilp Apartment
declared completion Dec 2022 · Nilratn Pandurang Javeri
Jivdani Vaibhavlaxmi
declared completion Dec 2023 · Kishor Bhaskar Patil
JK Heritage
possession by Dec 2027 · Vailankanni Realtors

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026