Mumbai/Project record

MahaRERA · the public record

JOLLITY LAVANYA

Palghar West · Jollity Lavanya Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 May 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 May 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000024506

Delivery and registration

When is the project declared for completion?

JOLLITY LAVANYA is registered with MahaRERA as P99000024506 and the promoter has declared completion for 29 May 2024.

29 May 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000024506
Registered on18 Feb 2020
Promoter-declared completion29 May 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JOLLITY LAVANYA record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jollity Lavanya Developers is the promoter of record on 5 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JOLLITY LAVANYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Jollity Lavanya1G+331 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 May 2024DUE TO COVID,NON AVAILABITY OF MATERIAL AND LABOUR

Location, Land & Connectivity

Located at Palghar West, Mahim Road, Vasai, Palghar, 401402. Per the filed land record, the plot is bounded to the north by S No-379, to the south by 7m Wide Road, to the east by Plot No-115 and to the west by Open Space. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Sanmukh Sunshine
Not filing quarterly progress reports · possession by Oct 2026 · Sanmukh Realty LLP
Bafna Luxuria
possession by Dec 2026 · Shrushti Developers
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Shakti Industrial Estate
Not filing quarterly progress reports · possession by Dec 2026 · Shakti Krupa Developers
Star Signature City-Star Emerald
possession by Dec 2026 · Star Builders & Developers

Other RERA-registered projects in Palghar

Jollity Olive
possession by Dec 2026 · Jollity Olives
Jollity Safalya
declared completion Mar 2025 · Safalya Realtors
Jollity Vijay Residency
declared completion Dec 2021 · Jollity Olives
Joyville Virar Phase 2
declared completion Sep 2022 · Joyville Shapoorji Housing Private Limit
Joyville Virar Retail
possession by Jun 2027 · Joyville Shapoorji Housing Private Limit
Judith Espana
possession by Dec 2026 · Judith Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026