Mumbai/Project record

MahaRERA · the public record

Joy City

Panvel · Prince Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000017285

Delivery and registration

When is the project declared for completion?

Joy City is registered with MahaRERA as P52000017285 and the promoter has declared completion for 29 Dec 2023.

29 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000017285
Registered on27 Jul 2018
Promoter-declared completion29 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Joy City record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Prince Developers is the promoter of record on 11 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Joy City in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Building No 51G+531 Dec 2021
Building No 4 A AND B WING1G+531 Dec 2021
Building no 21G+530 Sep 2021
Building No 31G+530 Sep 2021
Building no 11G+530 Sep 2021
Building No 61G+530 Sep 2021

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Joy City, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000026196318/07/2022Ronak Kishan Bharda vs PRINCE DEVELOPERSorder passed
CC1250155912/05/2025MRANAL SURENDRA MANDHANE vs Prince Developerspending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2023Due to a change in DP rules of MSRDC, the authority has issued a letter that there will be a delay in issuing OC from their end. Therefore we would request to please grant us an ex

Location, Land & Connectivity

Located at Panvel, Shedung, Andheri, Mumbai Suburban, 410221. Per the filed land record, the plot is bounded to the north by S No 118 42 Ex road, to the south by S No 51 Pond, to the east by S No 120 River and to the west by S No 128 132. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

The Highlands, Godrej City, Panvel
possession by Sep 2026 · Caroa Properties LLP
Jai Mata Di
possession by Nov 2026 · Vraj Developers
Ashtavinayak Diamond
possession by Dec 2026 · S G Group
Dharti Corner
possession by Dec 2026 · Dharti Buildcon
Majestic Krishna
possession by Dec 2026 · Krishna Builders And Developers
Payal Kalp
possession by Dec 2026 · V K Infra

Major developers building in Panvel

Other RERA-registered projects in Raigarh

JOY Villa Phase-2
declared completion Nov 2023 · Sadanand Laxmanrao Patil
Joy Villa Phase-I
possession by Dec 2026 · Sadanand Laxmanrao Patil
Jupiter Arihant
possession by Dec 2026 · Arjun Ashok Tarachandani
Jupiter Bliss
declared completion Sep 2026 · Arjun Ashok Tarachandani
Jupiter Heights
possession by Dec 2026 · Jupiter Heights
Jupiter Royal
possession by Nov 2026 · Arjun Ashok Tarachandani

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026