Mumbai/Project record

MahaRERA · the public record

K.E. HEIGHTS

JOGESHWARI WEST · KHURSHID EBRAHIM & SONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800053666

Delivery and registration

When is the project declared for completion?

K.E. HEIGHTS is registered with MahaRERA as P51800053666 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800053666
Registered on21 Nov 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for K.E. HEIGHTS record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Khurshid Ebrahim Sons is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In K.E. HEIGHTS, ₹2.11 Cr of a declared ₹10.11 Cr estimated project cost is reported as incurred, about 20.9%, as at the last certified filing with MahaRERA.

20.9%

₹2.11 Cr

of ₹10.11 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for K.E. HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
K E HEIGHTS1-31 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JOGESHWARI WEST, OFF S. V ROAD D P ROAD, Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by NALLAH, to the south by CTS NO 187, to the east by NALLAH and to the west by CTS NO 189 MERIDIAN HEIGHTS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park6 km
Bandra Kurla Complex (BKC)8 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

K.k.garment HUB
declared completion Mar 2025 · Shaista Khalil & Sons Developers Pri
K L Astoria
declared completion Dec 2025 · K L Housing LLP
K L Valeria
possession by Sep 2026 · K L Housing LLP
K M Enterprises
declared completion Dec 2020 · K M Enterprises
K Raheja Platinum
declared completion Dec 2018 · Dimple Enterprises
Kaatyayni Enclave
declared completion Mar 2018 · Starwing Developers Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026