Mumbai/Project record

MahaRERA · the public record

KANAK KUNJ

Mumbai City · MIHIKAA ENTERPRISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900004011

Delivery and registration

When is the project declared for completion?

KANAK KUNJ is registered with MahaRERA as P51900004011 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900004011
Registered on07 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KANAK KUNJ record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KANAK KUNJ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
KANAK KUNJ1G+14-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court MumbaiSUIT/5882/20072007Framing Of Issues
Dindoshi CourtSUIT/14545/20162016We Have Filed Notice Of Motion For Taking Our Written Statement Record
Small Causes Court BandraRAE/583/20052005Defandants Witness Going On

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400056. Per the filed land record, the plot is bounded to the north by ROAD NO 47, to the south by ROAD NO 45, to the east by PLOT NO 54 and to the west by ROAD NO 11. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)5 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle West

Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP
Meera Kunj
possession by Dec 2026 · Arham Realty

Other RERA-registered projects in Mumbai City

Kanakia Miami
declared completion Sep 2020 · Kanakia Spaces Realty Private Limited
Kanji Tower
declared completion Dec 2017 · Vijayaben Kanji Ashra
Kannamwar Nagar Panchsheel Chsl
possession by Jun 2028 · Prakritii Realtors LLP
Kapil Tirth
possession by Dec 2026 · Prathamesh Projects LLP
Karpur Heights
possession by Dec 2026 · Parvasha Grihnirman Sanstha
Kashinath
declared completion Dec 2023 · Qaswa Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026