Mumbai/Project record

MahaRERA · the public record

Kashihomes

Raigarh · KASHI HOMES PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Jul 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Jul 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000002764

Delivery and registration

When is the project declared for completion?

Kashihomes is registered with MahaRERA as P52000002764 and the promoter has declared completion for 01 Jul 2026.

01 Jul 2026

declared completion

2months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000002764
Registered on04 Aug 2017
Promoter-declared completion01 Jul 2026
Current statusCertificate Signed
Against todayabout 2 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Kashihomes record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Kashi Homes is the promoter of record on 93 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

93projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Kashihomes in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
sai puram1G+13-
sai siddhi1G+15-
sai ridhi1G+13-
sai ganesh1G+18-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Kashihomes, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000135017/10/2017NISHA MANOJ CHOUDHARI vs KASHI HOMES PVT LTDorder passed
CC00600000005764120/01/2019Maninderpal Singh Anand vs Kashi Homes Pvt Ltdorder passed
CC00600000005773020/01/2019Nitoo Singh Anand vs Kashi Homes Pvt Ltdorder passed
CC00600000039705212/08/2023KASHI HOMES PRIVATE LIMITED . vs MANINDERPAL SINGH ANANDorder passed
CC00600000039705312/08/2023KASHI HOMES PRIVATE LIMITED . vs NITOO SINGH ANANDorder passed

Location, Land & Connectivity

Located at Khalapur, Raigarh, 410203. Per the filed land record, the plot is bounded to the north by shanti nagar, to the south by road side, to the east by telephone exchange and to the west by samual mall. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort50 km
Bandra Kurla Complex (BKC)51 km
Powai / Hiranandani business park51 km
Lower Parel / Worli business district51 km
Chhatrapati Shivaji Int'l Airport53 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khopoli

Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers
Aakash Heights
possession by Dec 2026 · Aakash Lifespaces
Ashiyana Village Building No 10
possession by Dec 2026 · Ajaz Yusuf Khot

Other RERA-registered projects in Raigarh

Kasturi Aurelia
possession by Dec 2028 · M/s. Panache Realty
Kaustubh
possession by Jul 2027 · Vijay Jadhav Kadu
Kaveesha
declared completion Dec 2022 · SAI Developers
Kaveri Heights
declared completion Dec 2025 · Pradeep Ratan Patil
Kavya Hills
possession by Dec 2029 · B N Developers
Kavya Residency
possession by Dec 2027 · HJS Infrastructure LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026