Mumbai/Project record

MahaRERA · the public record

KCD AURA

BORIVALI WEST · TOWN KCD DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800032159

Delivery and registration

When is the project declared for completion?

KCD AURA is registered with MahaRERA as P51800032159 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800032159
Registered on14 Dec 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KCD AURA record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Town Kcd Developers is the promoter of record on 196 projects registered with MahaRERA, 19 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

196projects

registered with MahaRERA

19flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KCD AURA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
A WING1G+2431 Dec 2024
B WING1G+2431 Dec 2024
C WING1G+2431 Dec 2024
D WING1G+1831 Dec 2024

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for KCD AURA, with orders passed in 2 of them.

5complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000030373204/01/2023Kalpesh Navinchandra Shah vs Town KDC Developers LLPorder passed
CC1250425802/12/2025Yeshwant Shankar Jadhav vs TOWN KCD DEVELOPERS LLPorder passed
CC1260362312/06/2026Kalpesh Navinchandra Shah vs TOWN KCD DEVELOPERS LLPpending / no order on file
CC1260362412/06/2026Krishna Gokuldas Shah vs TOWN KCD DEVELOPERS LLPpending / no order on file
CC1260438814/07/2026Jatin Vinodbhai Kothari vs TOWN KCD DEVELOPERS LLPpending / no order on file

Location, Land & Connectivity

Located at BORIVALI WEST, RAM NAGAR, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by RAMNAGAR ROAD, to the south by EXISTING NALLA, to the east by ROAD and to the west by CTS NO 6B. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Swastik
possession by Sep 2026 · Reliance Corporation
Signet
possession by Oct 2026 · DG Builders

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

KCD Jogesh Eva
declared completion Dec 2025 · KCD Heritage Private Limited
KCD Lumin
declared completion Dec 2024 · KCD Heritage Private Limited
KCD Ridgewood
declared completion Sep 2023 · KCD Heritage PVT LTD
Kedar Darshan
possession by Apr 2027 · Kosmos Developers
Kedarnath
possession by Dec 2028 · Neeshiv Properties
Kedarnath Apartments
possession by Dec 2027 · Majestic Royale Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026