MahaRERA Property Intelligence · Mumbai Suburban

KCD AURA

P51800032159 · BORIVALI WEST · promoter Town Kcd Developers

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51800032159
Registered on14 Dec 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Town Kcd Developers is the promoter of record on 186 projects, of which 17 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
A WING1G+2431 Dec 2024
B WING1G+2431 Dec 2024
C WING1G+2431 Dec 2024
D WING1G+1831 Dec 2024

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000030373204/01/2023Kalpesh Navinchandra Shah vs Town KDC Developers LLPorder passed
CC1250425802/12/2025Yeshwant Shankar Jadhav vs TOWN KCD DEVELOPERS LLPorder passed
CC1260362312/06/2026Kalpesh Navinchandra Shah vs TOWN KCD DEVELOPERS LLPpending / no order on file
CC1260362412/06/2026Krishna Gokuldas Shah vs TOWN KCD DEVELOPERS LLPpending / no order on file
CC1260438814/07/2026Jatin Vinodbhai Kothari vs TOWN KCD DEVELOPERS LLPpending / no order on file

Location, Land & Connectivity

Located at BORIVALI WEST, RAM NAGAR, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by RAMNAGAR ROAD, to the south by EXISTING NALLA, to the east by ROAD and to the west by CTS NO 6B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Rishabraj Aradhana
possession by Jul 2026 · H Rishabraj Realty
SBI Ragvihar CHS
possession by Jul 2026 · Tuvin Consultancy LLP
Avyukta Neelkamal
possession by Sep 2026 · Shivoham Associates
Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

KCD Emerald
declared completion Jun 2024 · KCD Heritage Private Limited
KCD Jogesh Eva
declared completion Dec 2025 · KCD Heritage Private Limited
KCD Lumin
declared completion Dec 2024 · KCD Heritage Private Limited
KCD Ridgewood
declared completion Sep 2023 · KCD Heritage PVT LTD
KDO Chsl
possession by Nov 2026 · Sumukha Developers
Kedar Darshan
possession by Apr 2027 · Kosmos Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026