MahaRERA Property Intelligence · Raigarh

KESARI ANGAN

P52000006964 · promoter Gujar And Sheth

Certificate SignedDue 30 Dec 2024

Delivery & Registration

MahaRERA registrationP52000006964
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Gujar And Sheth is the promoter of record on 16 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
KESARI ANGAN B WING1G+331 Dec 2023
KESARI ANGAN A WING1G+431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mahad, Raigarh, 402301. Per the filed land record, the plot is bounded to the north by SURVEY NUMBER 101, to the south by SURVEY NUMBER 101, to the east by SURVEY NUMBER -101 and to the west by DEVELOPMENT ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~119 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort113 km
Lower Parel / Worli business district119 km
Bandra Kurla Complex (BKC)124 km
Chhatrapati Shivaji Int'l Airport126 km
Powai / Hiranandani business park127 km
Andheri MIDC / SEEPZ130 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana
Aditi Apartment
possession by Dec 2026 · Aijaz Ismail Darekhan

Other RERA-registered projects in Raigarh

Kesari Height
possession by Dec 2028 · Kesari Life Spaces
Keshar Exotica
possession by Dec 2027 · Keshar Developers
Keshar Gharonda
declared completion Mar 2023 · Keshar Developers
Keshar Kunj
declared completion Dec 2022 · Keshar Realities
Keshar Park
declared completion Jul 2022 · Shree Keshar Group
Keshav Kunj
declared completion Mar 2025 · Rajput Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026