Mumbai/Project record

MahaRERA · the public record

KHUSHI PARADISE

Govind Nagar · BHANUPRATAP BHARAT SINGH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700026370

Delivery and registration

When is the project declared for completion?

KHUSHI PARADISE is registered with MahaRERA as P51700026370 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

3months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700026370
Registered on11 Sep 2020
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KHUSHI PARADISE record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KHUSHI PARADISE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+48.

BuildingWingsFloorsDeclared completion
Khushi Paradise Wing A1G+4031 Dec 2025
Khushi Paradise Wing B1G+4831 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Govind Nagar, GRAMPANCHAYAT ROAD, Panvel, Raigarh, 421601. Per the filed land record, the plot is bounded to the north by Grampanchayat Road, to the south by S No 53 6, to the east by S No 51 and to the west by S No 53 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~58 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park58 km
Andheri MIDC / SEEPZ60 km
Chhatrapati Shivaji Int'l Airport64 km
Bandra Kurla Complex (BKC)65 km
Lower Parel / Worli business district73 km
Nariman Point / Fort79 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Kingsman Residency
possession by Jun 2028 · Shree Swastik Constructions
Kiran Enclave
possession by Mar 2029 · S K Raghuraaj
Kiran Heights
possession by Mar 2030 · Bansikailas Estates LLP
Kisan Heights
possession by Sep 2027 · Pravin Kisan Bhoir
Kisan Vihar
declared completion Feb 2025 · Vinod Builder
Kishin Mahal CO Operative Society
possession by Dec 2028 · Kishin Mahal CO OP HSG Society Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026