KOHINOOR CITY PHASE 1

JASVALI · KOHINOOR ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000028271

Delivery and registration

When is the project declared for completion?

KOHINOOR CITY PHASE 1 is registered with MahaRERA as P52000028271 and the promoter has declared completion for 31 Jan 2024.

31 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000028271
Registered on18 Feb 2021
Promoter-declared completion31 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KOHINOOR CITY PHASE 1 record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kohinoor Associates is the promoter of record on 40 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

40projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KOHINOOR CITY PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
KOHINOOR CITY1G+531 Jul 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JASVALI, JASVALI, Shrivardhan, Raigarh, 402110. Per the filed land record, the plot is bounded to the north by GAT NO 412 413, to the south by GAVTHAN, to the east by ROAD GAT NUMBER 414 and to the west by GAT NO 532. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kohinoor Associates is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Bhoste

Avenues
possession by May 2029 · Silver Homes Enterprises
Punir Gaurav - B Wing
declared completion Apr 2026 · Punir Gaurav Developers Pvt Ltd.
Sagar Vihar
declared completion Mar 2026 · Core Developers
Bandal VED Bhumi-Phase 2
declared completion Apr 2025 · Not Available
Kundan Darshan Apartment
Past its declared completion date · declared completion Jun 2023 · Amarkumar Javerchand Jain
Ganleela Apartment
declared completion Dec 2021 · Vishal Vimal Jain

Other RERA-registered projects in Raigarh

Kohinoor Plaza
possession by Mar 2028 · Phoenix Builders And Developers
Kohinoor Residency
possession by Sep 2027 · M T Builders
Kokan Residency
declared completion Dec 2019 · Smile Intra Trade Private Limited
Kolad Hills
declared completion Dec 2025 · Saifortune Builders AND Developers Priva
Komal
declared completion Dec 2025 · Prasad Construction
Konnark Astra
possession by Dec 2033 · Konnark Zenith

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026