MahaRERA Property Intelligence · Raigarh

KOLAD HILLS

P52000017292 · KOLAD · promoter Saifortune Builders And

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP52000017292
Registered on31 Jul 2018
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Saifortune Builders And is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
D-WING1G+931 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KOLAD, DIVISION COLONY, Roha, Raigarh, 402304. Per the filed land record, the plot is bounded to the north by G NO 161, to the south by G NO 183, to the east by G NO 169 and to the west by G NO 166. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Saifortune Builders AND Developers Private Limited is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Saifortune Builders AND Developers Private LI

Saifortune Builders AND Developers Private Limited
FlaggedRaigarh

Other RERA-registered projects in Warasgaon

Ekdanta Plaza
possession by Dec 2026 · Ekdanta Realtors
Prerana Heights
possession by Dec 2029 · Not Available
Lush
Not filing quarterly progress reports · declared completion Jun 2026 · Smita Rajan Akshekar
Kolad Hills
declared completion Dec 2025 · Saifortune Builders AND Developers Priva
SAI Shubharambh Residency
Not filing quarterly progress reports · declared completion Dec 2025 · Shreeraj Asmi Infra LLP
Malusare Residency
declared completion Oct 2025 · Sandeep Enterprises

Other RERA-registered projects in Raigarh

Komal
declared completion Dec 2025 · Prasad Construction
Kondvilkar Heights
declared completion Jun 2022 · Shree Yogeshwari Developers Private Limi
Konnark Astra
possession by Dec 2033 · Konnark Zenith
Konnark Gardens
declared completion May 2022 · Ninath Bhausaheb Shingade
Konnark Harmony
possession by Nov 2027 · Konnark Develeco
Konnark Heavens
declared completion Mar 2023 · Ninath Bhausaheb Shingade

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026