Krishna Pride

CHANAKYA NAGAR · Gajanan Krupa Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700011439

Delivery and registration

When is the project declared for completion?

Krishna Pride is registered with MahaRERA as P51700011439 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700011439
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Krishna Pride record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gajanan Krupa Developers is the promoter of record on 153 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

153projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Krishna Pride in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+36.

BuildingWingsFloorsDeclared completion
Sheth Sakharam Tower1G+3630 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at CHANAKYA NAGAR, ADHARWADI JAIL ROAD, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by 520 sqmt out of SNO 54 1A, to the south by Remaining area ofSNo 54 1A, to the east by Road and SNo 55A Gurcharan Land and to the west by SNo 54 1 B belonging to tukaram karbhari and other. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ31 km
Chhatrapati Shivaji Int'l Airport34 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district43 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Krishna Residency
declared completion Dec 2021 · Shree Balaji Developers
Krishna Sadan
possession by Jul 2027 · SAI Shardha Developers
Krishna Sankul B Wing
declared completion Dec 2025 · M/S Krishna Enterprises
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Spaces
declared completion Jun 2022 · Magnum Solitaire LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.