MahaRERA Property Intelligence · Thane

KRISHNA VILLA

P51700019210 · GOLWALI · promoter Royal Builders Developers

Certificate SignedDue 01 Dec 2023

Delivery & Registration

MahaRERA registrationP51700019210
Registered on09 Jan 2019
Promoter-declared completion01 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Royal Builders Developers is the promoter of record on 172 projects, of which 26 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
KRISHNA VILLA1G+101 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at GOLWALI, GOLWALI, Kalyan, Thane, 421203. Per the filed land record, the plot is bounded to the north by ACCORDING TO RECORD OF RIGHTS, to the south by ACCORDING TO RECORD OF RIGHTS, to the east by ACCORDING TO RECORD OF RIGHTS and to the west by ACCORDING TO RECORD OF RIGHTS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Royal Builders & Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Hedutane

Fiora F
possession by Aug 2026 · Lodha Developers Limited
Liana D
possession by Aug 2026 · Lodha Developers Limited
Ambrin 3
possession by Sep 2026 · Impressions
Liana C
possession by Sep 2026 · Lodha Developers Limited
Casa Belvedere
possession by Oct 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Hedutane

Other RERA-registered projects in Thane

Krishna Wing C
possession by Dec 2029 · K Rudraksh Realtors LLP
Krishnai Vani Complex
declared completion Dec 2025 · Stone House Developer
Krishnakalp
declared completion Dec 2023 · Shivam Enterprises
Krishnalaya
declared completion Dec 2019 · Satheeshkumar K Nair
Krishnalaya
declared completion Jun 2024 · Adwait Realty
Krishnapingaksha
possession by Dec 2026 · Prashant Tukaram Baeet

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026