Mumbai/Project record

MahaRERA · the public record

LA-IMPERO A AND B BUILDING

HOTEL RIDDESH · Kytek Homes and Infra Structure Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000010268

Delivery and registration

When is the project declared for completion?

LA-IMPERO A AND B BUILDING is registered with MahaRERA as P52000010268 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000010268
Registered on24 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LA-IMPERO A AND B BUILDING record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LA-IMPERO A AND B BUILDING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
LA-IMPERO A BUILDING1G+8-
LA-IMPERO B BUILDING1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at HOTEL RIDDESH, MUMBAI-GOA HIGHWAY, Andheri, Mumbai Suburban, 402301. Per the filed land record, the plot is bounded to the north by S NO 22A, to the south by NATIONAL HIGHWAY 17, to the east by S NO 25 and to the west by S NO 147 2A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~120 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort114 km
Lower Parel / Worli business district120 km
Bandra Kurla Complex (BKC)124 km
Chhatrapati Shivaji Int'l Airport127 km
Powai / Hiranandani business park128 km
Andheri MIDC / SEEPZ131 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
Rukaiya Residence
possession by Dec 2026 · Vision Developers
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana

Other RERA-registered projects in Raigarh

LA MER ONE
possession by Mar 2029 · La Mer Homes LLP
La Mer One Phase - II
possession by Dec 2030 · La Mer Homes LLP
La Mer One Phase III
possession by Mar 2031 · La Mer Homes LLP
LA Meridian - Pimpale Grand
declared completion Dec 2025 · LA Meridian
LA Queen
declared completion Dec 2023 · Calidad Lifespaces LLP
Labdhi Gardens Phase 10
possession by Dec 2027 · Labdhi Lifestyle Limited

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026