Mumbai/Project record

MahaRERA · the public record

LAXMI RESIDENCY

RAGHOJI NAGAR CHERPOLI NEAR VIHAN HONDA SHOWROOM · SANJAY DAULAT WADILE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

12 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

12 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700014922

Delivery and registration

When is the project declared for completion?

LAXMI RESIDENCY is registered with MahaRERA as P51700014922 and the promoter has declared completion for 12 Mar 2022.

12 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700014922
Registered on11 Jan 2018
Promoter-declared completion12 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LAXMI RESIDENCY record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LAXMI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
B TYPE1G+5-
C TYPE1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2020BASICALLY ONSITE 90% WORK HAS BEEN COMPLETED, WE ARE IN PROCESS FOR FINALISING THE WORK THE WORK IS DELAYED DUE TO DELAYED DUE TO NON AVAILABILITY OF SAND.
30 Sep 202012 Mar 2022Due to Covid -19 Pandamic non availability of Labours and Materials

Location, Land & Connectivity

Located at RAGHOJI NAGAR CHERPOLI NEAR VIHAN HONDA SHOWROOM, CHERPOLI SHAHAPUR MAJOR DISTRICT ROAD, Shahapur, Thane, 421601. Per the filed land record, the plot is bounded to the north by GUT NO 146 149 151, to the south by EXISTING ROAD, to the east by CHERPOLI SHAHAPUR MAJAOR DISTRICT ROAD NO 61 and to the west by GUT NO 140. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~58 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park58 km
Andheri MIDC / SEEPZ60 km
Chhatrapati Shivaji Int'l Airport63 km
Bandra Kurla Complex (BKC)65 km
Lower Parel / Worli business district73 km
Nariman Point / Fort79 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Laxmi Residency
possession by Dec 2026 · Laxmi Infra
Laxmi Shankar Complex
possession by Jun 2028 · Aditi Buildwell
Laxmi Solitaire
possession by Jun 2028 · Laxmi Construction Co
Laxmideep Chsl
possession by Dec 2026 · Rudraa Developers
Laxmivihar CO-Operative Housing Society Limited
possession by Dec 2029 · Shree Saraswati Developers
Leaf Mount
possession by Dec 2029 · Infinity Infra

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026