Mumbai/Project record

MahaRERA · the public record

MAN EXCELLENZA

Mumbai Suburban · MAN INFRAPROJECTS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Feb 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007139

Delivery and registration

When is the project declared for completion?

MAN EXCELLENZA is registered with MahaRERA as P51800007139 and the promoter has declared completion for 28 Feb 2021.

28 Feb 2021

declared completion

67months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007139
Registered on17 Aug 2017
Promoter-declared completion28 Feb 2021
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAN EXCELLENZA record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Man Infraprojects Limited is the promoter of record on 75 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

75projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAN EXCELLENZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
MAN EXCELLENZA1G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for MAN EXCELLENZA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005628103/10/2018RAKESH KUMAR PANDEY AND VINITA RAKESH PANDEY vs MAN INFRAPROJECTS LIMITEDorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Arbitration002016Pending
Bombay City Civil And Sessions Court893/20152015Hearing Pending
Bombay City Civil And Sessions Court518/20172017Hearing Pending

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400056. Per the filed land record, the plot is bounded to the north by N 19D 5M 49point92361S - E 72D 50M 23point84758S, to the south by N 19D 5M 48point54870S - E 72D 50M 22point79393S, to the east by N 19D 5M 48point45889S - E 72D 50M 23point73083S and to the west by N 19D 5M 50point12944S - E 72D 50M 22point81191S. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)5 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle West

Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP
Meera Kunj
possession by Dec 2026 · Arham Realty

Other RERA-registered projects in Mumbai Suburban

Manas
declared completion Dec 2023 · Sstc India Constructions
Manasarovar
declared completion Mar 2026 · Harasiddh Projects
Mandor Bliss
possession by Dec 2028 · Mandor Home Villa LLP
Mandor Solitaire
declared completion Feb 2026 · Sanket Kiritkumar Jain
Manek Terrace CHS LTD
declared completion Oct 2020 · K T Group
Mangal Business Park - Gautam Apartment
possession by Mar 2027 · Mangal Buildhome Private Limited

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026